TABLE OF CONTENTS
Descriptive Summary
Biographical Sketch
Scope and Content
Organization
Restrictions
Index Terms
Related Material
Administrative Information
Description of Series
Manuscripts
|
Physical Plant:
An Inventory of Its Records, 1937-2008, at the Southwest
Collection/Special Collections Library
| | |
|
|
| Creator | Texas Tech University |
| Title: | Physical Plant,
|
| Dates: | 1937-2008 |
| Abstract: | The collection
contains records of the Physical Plant at Texas Tech University dating from
1937-2008. |
| Collection # | U 294.2 |
| Quantity: | 94 boxes (94.0 linear
feet) |
| Language | English |
| Repository: | Southwest Collection/Special Collections
Library, Texas Tech University |
The Physical Plant consists of many departments, shops, and employees
who are dedicated to insuring that Texas Tech has the resources it needs to
maintain all buildings and functions, runs efficiently, and looks good for the
community, students, faculty, and staff. They are responsible for the
maintenance and repair of education and general building structural,
mechanical, utility and electrical infrastructure.
Return to the Table of Contents
This 94 box collection is divided into three series. Series one of the
collection consists of two boxes of files on the 1997-1998 renovation of the
Administration Building's west wing. Series two includes bound project
specification manuals for Texas Tech buildings. Series three consists of
project files including correspondence, photographs, and blueprints, relating
to Physical Plant projects around campus.
Return to the Table of Contents
| | |
Organization
|
| Series one and three are arranged according to the Physical Plant's
original order. Series two is arranged chronologically by building or
department. |
| Due to the size of the inventory, this finding aid has been split up into two files: |
| Physical Plant Boxes #1-55 |
| Physical Plant Boxes #56-94 |
Return to the Table of Contents
Access Restrictions
Open for research
Return to the Table of Contents
| | |
|
|
| The subject headings used by the Southwest Collection/Special
Collections Library are derived from the Library of Congress and/or locally
developed. |
| Subjects (Organizations) |
| | Texas Tech
University--Buildings |
| | Texas Tech University--Buildings--Design
and construction |
| | Texas Tech
University--Buildings--Designs and plans |
| | Texas Tech University--Buildings,
structures, etc. |
| Subjects (Places) |
| | Lubbock (Tex.) |
| Subjects |
| | Architecture--Texas--Lubbock |
| | Campus planning--Texas--Lubbock |
| | College
buildings--Texas--Lubbock |
| | College
facilities--Texas--Lubbock--Planning |
| | Public buildings--Design |
Return to the Table of Contents
| | |
|
Physical Plant Records, 1994-2004, Southwest Collection/Special
Collections Library, Texas Tech University, Lubbock, Texas.
|
Return to the Table of Contents
Physical Plant, 1937-2008, Southwest Collection/Special Collections
Library, Texas Tech University, Lubbock, Texas
Collection accession #(s):
2008-0138-B, 2008-0139-B, 2008-0141-B
Donated, 2008
Denise Rojas, Anup Tavkar, and Katie Long, May 2009
Return to the Table of Contents
| | | | | | | | | | | | | |
| |
Manuscripts
|
| | | Series Two continued |
| box | folder |
| 56 | 1 | | | University Police Department Asbestos Abatement and
Demolition 97-43,
1998 |
| 2 | | | University Police Department Asbestos Abatement,
2003 |
| 3 | | | University Police Department Building Modifications,
2003 |
| 4 | | | Urbanovsky Park Landscape Irrigation,
1996 |
| 5 | | | Urbanovsky Park Student Amphitheater Colored Paving,
1996 |
| 6 | | | Utility Distribution Plant #1,
1980 |
| 7 | | | Wall/Gates: Dormitory and Dining Facilities for Women
HHFA Project # CH-Tex-150(D),
1961 |
| 8 | | | Wall/Gates Generator 83-10C,
1983 |
| 9 | | | Wall/Gates Washer 83-10B,
1983 |
| 10 | | | Wall/Gates and Hulen/Clement Halls Parking Lot
Expansion,
1991 |
| 11 | | | Wall/Gates Roof Repairs FPC 92-13,
1993 |
| 12 | | | Wall/Gates Accessible Room Renovations HDS94-1,
1994 |
| 13 | | | Wall/Gates Common Area Roofs FPC 93-33,
1994 |
| 14 | | | Wall/Gates and Hulen/Clement Halls Kitchen Waste Line
Rehabilitation #120525CR,
1998 |
| 15 | | | Wall/Gates Replace West Wing Roof #01962,
2001 |
| 16 | | | Water Treatment System (D.I./R.O.) Devro-Lubbock,
1976 |
| 17 | | | Water Distribution Improvements,
1983 |
| box | folder |
| 57 | 1 | | | Installation of Water Chiller and Cooling Tower,
1983 |
| 2 | | | Sewage Effluent Reservoir,
1984 |
| 3 | | | Campus Replacement of Water Meters,
1996 |
| 4 | | | 19th and Univeristy Irrigiation,
1996 |
| 5 | | | Replacement Campus Water Meters Phase 2,
1997 |
| 6 | | | Electrical Distribution for Weeks Hall,
1982 |
| 7 | | | Weeks Exterior Doors, 2 Blueprints,
1989 |
| 8 | | | WEM Computerized Control System W-8407,
1983 |
| 9 | | | West Hall Renovation,
1979 |
| 10 | | | West Hall Copy Tech Renovation Tech Press,
1985 |
| 11 | | | West Hall Asbestos Abatement and Window Replacement
98-22A,
1999 |
| 12 | | | West Hall New Visitors Center FPC 98-22,
1999 |
| 13 | | | West Hall New Visitors Center Moving Services FPC
98-22M,
1999 |
| 14 | | | West Hall New Visitors Center Temporary Quarters
FPC98-22T,
1999 |
| 15 | | | West Hall Room 105 Renovation PP01834,
2001 |
| box | folder |
| 58 | 1 | | | West Hall Visitors Center Terrazzo Floor Replacement
#05-050006,
2005 |
| 2 | | | Recreation Facilities West of Flint Avenue Field
Sports,
1974 |
| 3 | | | West Recreational Field Sport Lighting,
1974 |
| 4 | | | West Recreation Fields Concrete paving, Backstops and
Fencing 85-93C,
1986 |
| 5 | | | West Recreation Fields Irrigation,
1986 |
| 6 | | | West Recreation Fields Lighting Project Manuals
#85-93B,
1986 |
| 7 | | | West Recreation Area Construction of Parking Lot,
1988 |
| 8 | | | West Recreation Fields Phase 2 Lighting Project
Manual, 2 Blueprints,
1991 |
| 9 | | | West Wing HVAC,
1997 |
| 10 | | | West Wing Renovation Rebid,
1997 |
| 11 | | | Weymouth/Chitwood Replace Hot Water Lines FPC 86-35,
1987 |
| 12 | | | Weymouth Coleman, Stangel/Murdough Booster Pump
Replacement FPC 97-16, Blueprints,
1997 |
| 13 | | | Weymouth/Bledsoe/Horn Halls Elevator
Modernization/Renovation,
1997 |
| 14 | | | Weymouth and Chitwood Halls Replacement of Hot Water
Heaters #6619-005-A01,
1998 |
| 15 | | | Weymouth/Chitwood Halls Replace Hot Water Heaters,
119847CR,
1998 |
| 16 | | | Weymouth, Bledsoe and Horn Dormitories Elevator
Renovations, 1 of 2,
1998 |
| 17 | | | Weymouth, Bledsoe and Horn Dormitories Elevator
Renovations, 2 of 2,
1998 |
| 18 | | | Wiggins Complex Built in Furniture,
1966 |
| 19 | | | Wiggins Complex: Elevator Equipment,
1966 |
| 20 | | | Wiggins Complex: Food Service Equipment,
1966 |
| 21 | | | Wiggins Complex General Construction,
1966 |
| box | folder |
| 59 | 1 | | | Wiggins Dormitory Complex Parking Facilities Phase 1,
1967 |
| 2 | | | Wiggins Complex, Energy Conserving HVAC Revisions,
1981 |
| 3 | | | Wiggins Dormitory, Energy Conserving HVAC Revisions
Phase 2,
1981 |
| 4 | | | Wiggins Residence Hall Fire Alarm System Phase 1,
1982 |
| 5 | | | Wiggins Residence Hall Complex Fire Alarm System Phase
2 82-21,
1982 |
| 6 | | | Wiggins Residence Hall Dining Room Renovations 81-54,
1983 |
| 7 | | | Wiggins Washer 83-10A,
1983 |
| 8 | | | Wiggins Complex Preheat Coil Replacement 85-08,
1985 |
| 9 | | | Wiggins Residence Complex Fire Alarm System Repair and
Restoration FPC 86-49,
1986 |
| 10 | | | Wiggins Kitchen Sewer Renovation FPC 86-04,
1986 |
| 11 | | | Wiggins Kitchen Sewer Renovation Phse 2 FPC 86-44,
1986 |
| 12 | | | Wiggins Roof Replacement FPC 8631,
1987 |
| 13 | | | Wiggins Trash Chute Repairs FPC 8646,
1987 |
| 14 | | | Wiggins Kitchen Hot Water Heater Replacement 89-11,
1989 |
| 15 | | | Wiggins Kitchen Hot Water Heater Replacement Asbestos
Abatement FPC 8911/11, Blueprints,
1989 |
| 16 | | | Wiggins Landscape Phase 3 Concrete, Earth, and
Brickwork,
1989 |
| 17 | | | Wiggins Dining Pass West Roof FPC 93-07,
1993 |
| 18 | | | Wiggins Complex Fire Protection Upgrade Phase 2 FPC
98-28,
2000 |
| 19 | | | Wiggins Dining Complex Career Center 01939,
2002 |
| 20 | | | Wiggins Dining Complex Career Center Reroofing
PP02637,
2002 |
| 21 | | | Women's Gym Specifications,
1959 |
| 22 | | | Women's Gym Basement Ventilating System,
1961 |
| 23 | | | Women's Gym Dance Floor Replacement FPC 8913,
1991 |
| | | Series Three |
| box | folder |
| 60 | 1 | | | New Deal Farm, Mechanical Flush, 2 prints,
1989 |
| 2 | | | Aquatic Center, Recirculation Pump,
1992 |
| 3 | | | Food Sciences, FP and C 92-04, Replace Fume Hood and
Fan,
1992 |
| 4 | | | Development Office, CR038538, Replace Roof, 6 prints,
1996 |
| 5 | | | New Deal Farm, CR048809, Renovation, 40 prints,
1996 |
| 6 | | | Student Rec Center, Roof Warranty,
1996 |
| 7 | | | Business Administration, CR068412, Replace Campus
Water Meters,
1997 |
| 8 | | | Campus Utilities, CR068412, Replace Campus Water
Meters,
1997 |
| 9 | | | Gaston Hall, FP and C 97-19, Replace Roof,
1997 |
| 10 | | | Math, CR021514 and FP and C 93-30, Replace Roof,
1997 |
| 11 | | | New Deal Farm, CR081993, Renovate Existing Feed Mill,
15 prints, 1 of 2,
1997 |
| 12 | | | New Deal Farm, CR081993,Renovate existing Feed Mill, 2
blueprints, 2 of 2,
1997 |
| 13 | | | New Deal Farm, CR095908, Evaluate lighting-Bldg 820,
1997 |
| 14 | | | Student Rec Center, CR054356, Replace Roof,
1997 |
| 15 | | | Aquatic Center, CR080737, Replace Circulation
Pipe-Pump Room,
1998 |
| 16 | | | Campus Interior Painting, CR091365, Paint West Hall,
Drane, Computer Center,
1998 |
| 17 | | | Campus Tunnels, CR114114, Replace Steam Expansion
Joints,
1998 |
| 18 | | | Campus Tunnels, CR117103, Replace Steam Expansion
Joint between rack 1550 and 1510,
1998 |
| 19 | | | Law, CR083797, Replace Fixed Classroom Seating Room
105,
1998 |
| 20 | | | Law, CR083998, Replace Fixed Classroom Seating,
1998 |
| 21 | | | Museum, CR086195, Construct office for Dr. Schmidly,
1998 |
| 22 | | | National Guard Armory, CR119021, TDLR Reply,
1998 |
| 23 | | | New Deal Farm, CR105456, Replace Inflatable Screens,
1998 |
| 24 | | | Physical Plant, CR084755 and CR112244, Replace Roofs
on Traffic and Parking Annex and Grounds Maintenance Sheds,
1998 |
| 25 | | | Science, CR084984, Upgrade Electrical Service-Room
104, 106 and 108,
1998 |
| 26 | | | Science, CR119016, Renovate Room 203 and 310 for
Computer Lab,
1998 |
| 27 | | | Sewer Lift Station, CR105482 Replace Pumps,
1998 |
| 28 | | | Student Rec Center, CR058667, Upgrade Lighting-Main
Gym,
1998 |
| 29 | | | Student Rec Center, CR101236, Elevator Contract
Administration,
1998 |
| 30 | | | Student Rec Center, Replace Roof-Phase 3,
1998 |
| 31 | | | University Center, CR076774, Correct Elevator Code
Deficiencies,
1998 |
| 32 | | | University Center, CR077810, Renovate Cappuccinos,
1998 |
| 33 | | | University Center, CR101381, Install Secondary Oil
Containment,
1998 |
| 34 | | | University Center, CR112488, Renovate Lighting in Game
Room 10-0006,
1998 |
| 35 | | | University Theatre, CR084758, Replace Lighting,
Dimmers, and Circuits,
1998 |
| 36 | | | University Theatre, CR110166, Add Stalls to Restroom,
1998 |
| 37 | | | UPD-University Police Department, CR103582, Move to
Different Facility,
1998 |
| 38 | | | West Hall, CR102756, Redesign Financial Aid Lobby Room
310,
1998 |
| 39 | | | Women's Gym, CR086461, Replace EMS,
1998 |
| 40 | | | Women's Gym, CR118906, Evaluate Lighting,
1998 |
| box | folder |
| 61 | 1 | | | Ag Sciences, #01133, Renovate Room 202,
1999 |
| 2 | | | Architecture, CR120444, Renovate Studio and
Classrooms,
1999 |
| 3 | | | Campus Elevators, CR120556, CR120577-580, 00315,
Upgrade Elevators,
1999 |
| 4 | | | Campus Tunnels, CR117180, Abate Expansion Joints
CHACP1 to Biology and BA,
1999 |
| 5 | | | CHACP II, CR111568, Replace Boiler Blow-down system,
1999 |
| 6 | | | CHACP II, CR119713, Replace Surge Tank,
1999 |
| 7 | | | Chemistry, CR119823, Carpet Room 49,
1999 |
| 8 | | | Coleman Hall, CR112957, Chute Fire Protection System,
1995 |
| 9 | | | Foreign Language, CR107524, Energy Audit,
1999 |
| 10 | | | Human Sciences, CR118905, Campus Building Interior
Painting Phase 3,
1999 |
| 11 | | | Mass Communications, CR112998, Energy Audit,
1999 |
| 12 | | | McClellan Hall, CR112008, Elevator Renovation, 1 of 2,
1999 |
| 13 | | | McClellan Hall, CR112008, Elevator Renovation, 2 of 2,
1999 |
| 14 | | | Merket Alumni Center, CR090113, Roof Warranty,
1999 |
| 15 | | | New Deal Farm, CR120649, Replace HVAC 2 offices West
Side,
1999 |
| 16 | | | Physical Plant, CR118306, Relocation of Work Control,
1999 |
| 17 | | | Physical Plant, CR120093, Convert Traffic and Parking,
undated |
| 18 | | | Physical Plant, CR120244, HVAC Control and Window
Shade,
1999 |
| 19 | | | Ranching Heritage, #00004, Remove Wall between room
106B and 106C,
1999 |
| 20 | | | Ranching Heritage, CR120603, Move LP and L
Tranformers,
1999 |
| 21 | | | Ranching Heritage, CR120646, Provide Conduit from
Museum to RHC,
1999 |
| 22 | | | Ranching Heritage, CR120659, Inspection of Los
Corralitos,
1999 |
| 23 | | | Reese Center, CR120258, Repair/Replace Roof on Bldg.
#552,
1999 |
| 24 | | | Reese Center, CR120719, Make 8x10 Bronze Plaque,
1999 |
| 25 | | | Science #00101, Renovate Room 118,
1999 |
| 26 | | | Sceince, #CR065958, Upgrade EMS,
1999 |
| 27 | | | Science, CR078016, Investigate Radio Frequency Noise
South Wing,
1999 |
| 28 | | | Science, CR082787, Electric Load Elevation,
1999 |
| 29 | | | Science, CR094604, Renovate Room 7 Sound Attenuation,
1999 |
| 30 | | | Science, CR120483, Install Laser Interlocks Rooom 108,
1999 |
| 31 | | | Southwest Collection/Special Collections Library,
CR103034, Extend Electrical Service Room 107,
1999 |
| 32 | | | Southwest Collection/Special Collections Library,
CR120023, Install Backup Air Compressor,
1999 |
| 33 | | | Southwest Collections/Special Collections Library,
CR120269, Exterior Sign,
1999 |
| 34 | | | Student Rec Center, CR066939, Repair Roof Area "B",
1999 |
| 35 | | | Student Rec Center, CR076772, Elevator Machine Room
Ventilation,
1999 |
| 36 | | | Student Rec Center, CR084230, Utilities for
Washer/Dryer,
1999 |
| 37 | | | Student Rec Center, CR099702, Repair Roof Gym,
1999 |
| 38 | | | Student Rec Center, CR120526, Electric Power for
Scoreboard,
1999 |
| 39 | | | Student Rec Center, CR120632, Replace Coil North
Equipment Room,
1999 |
| 40 | | | Student Rec Center, CR120762, Install Phone in
Elevator,
1999 |
| 41 | | | Texas Tech Police, CR119132, Add HVAC to Room 115A and
118,
1999 |
| 42 | | | United Spirit Arena, CR120329, Hook up Steam Dryer in
Laundry Room,
1999 |
| 43 | | | University Center, CR101380, Correct Code
Deficiencies,
1999 |
| 44 | | | University Center, CR101382, Contract Administration,
1999 |
| 45 | | | University Center, CR101959, Increase Fan Output,
1999 |
| 46 | | | University Center, CR120761, Install Phones in
Elevator,
1999 |
| 47 | | | University Theatre, CR120696, Construct Costume Shop
Addition,
1999 |
| 48 | | | Wall-Gates Hall, CR120529, Repair Gates Elevator #2,
1999 |
| 49 | | | West Hall, CR087581, Automate Interior Doors,
1999 |
| 50 | | | West Hall, CR099214, Update Interior Signage,
1999 |
| 51 | | | West Hall, CR120402, Repair Separation of Elevator
Shaft from Building,
1999 |
| 52 | | | West Hall, #CR120601, Renovate Make-Up Air System,
1999 |
| 53 | | | West Hall, #CR120726, Renovate Room 244A,
1999 |
| 54 | | | Wiggins Dining, #CR120749, Replace A/H Room 9,
1999 |
| 55 | | | Wind Engineering, #CR119956, Provide Grounding System,
1999 |
| 56 | | | Administration, #00549, Purchase Lateral Filing
Cabinets,
2000 |
| 57 | | | Admin, #00828, Install new Carpet in chancellor's
office,
2000 |
| 58 | | | Administration, #01075, Renovate Room 41,
2000 |
| 59 | | | Administration, #01623, Repair Carpet room 112, 125,
341 and Women's Restroom,
2000 |
| 60 | | | Administration, CR120267, New Furniture room 104D,
2000 |
| 61 | | | Administration, Furniture For President's Suite, Ste
150,
2000 |
| 62 | | | Ag Sciences, #00393, Renovate Room 205A,
2000 |
| box | folder |
| 62 | 1 | | | Agricultural Education, CR118059, Energy Audit,
2000 |
| 2 | | | Annual Carpet,
2000 |
| 3 | | | Aquatic Center, #00980, Install Shutoff of Caustic
Delivery Pump, 4 prints,
2000 |
| 4 | | | Aquatic Center, #01342, Replace Electrical Switchband,
2000 |
| 5 | | | Architecture, #00830, Carpet 10th Floor hallway,
2000 |
| 6 | | | Architecture, #00904, Add Walls, Electrical outlets
and data drops,
2000 |
| 7 | | | Art, #00156, Build Enclosure-Room SB3A,
2000 |
| 8 | | | Art, #00991, Remodel Room 101,
2000 |
| 9 | | | Art, #01161, Repair Overhead Walkway on East Side,
2000 |
| 10 | | | Biology, #00923, Install Emergency Lighting in LH100,
EM Lab and Animal Room,
2000 |
| 11 | | | Biology, CR098893, Elevator Modernization,
2000 |
| 12 | | | Biology, CR118256, Replace Lecture Hall Roof,
2000 |
| 13 | | | Bledsoe, Horn, and Weymouth Halls, CR100045, Elevator
Modernization,
2000 |
| 14 | | | Business Administration, #00832, Annual Carpet in
Elevators; Rm 503,
2000 |
| 15 | | | Business Administration, #00943, Patch Carpet,
2000 |
| 16 | | | Business Administration, #01359, Interior Upgrades,
2000 |
| 17 | | | Campus, #01709, Install Fiber Optics, Electrical
Carillons in 5 campus locations,
2000 |
| 18 | | | Campus Elevators, #00214, Elevator Maintenance
Service,
2000 |
| 19 | | | Campus Elevators, #00523, Provide elevator blueprints
for machine rooms,
2000 |
| 20 | | | Campus Exterior Lighting, #01002, Wiggins Complex:
Investigate Lighting for Security,
2000 |
| 21 | | | Campus Irrigation, #01175, Improve Campus irrigation,
2000 |
| 22 | | | CHACP1, #00148, Create Area for Safety Office,
2000 |
| 23 | | | CHACP1, #00306, Repair Freight Elevator,
2000 |
| 24 | | | CHACP 1, #00791, Install Permanent Wall in Main
Electrical Breaker Room,
2000 |
| 25 | | | CHACP 1, CR120765, Asbestom Abatement 80 PSI Steam
Header,
2000 |
| 26 | | | Chancellor's Residence, #01110, Add Landscape
Lighting,
2000 |
| 27 | | | Chemical Engineering, #01053, Hook up Fume Hood in
room 6-1,
2000 |
| 28 | | | Chemical Engineering, #01380, Renovate Room 202, 205,
207, 209, 211,
2000 |
| 29 | | | Chemical Engineering, #01381, Convert Room B-1 to Lab
Space,
2000 |
| 30 | | | Chemical Engineering, #01382, Convert B-4 to Grad
Student Offices,
2000 |
| 31 | | | Chemical Engineering, #01386, Remodel main office 204
to reception area,
2000 |
| 32 | | | Chemical Engineering, #01387, Convert room 105, 107,
109, to Faculty offices,
2000 |
| 33 | | | Chemical Engineering, CR120604,
2000 |
| 34 | | | Chemistry, #00406, Install new Emergency
lighting-south addition,
2000 |
| 35 | | | Chemistry, #01055, Upgrade Fire Alarm System,
2000 |
| 36 | | | Chemistry, #01151, Upgrade HVAC System,
2000 |
| 37 | | | Chemistry, CR097298, Renovate Rooms B003/004 for Laser
Lab,
2000 |
| 38 | | | Child Development Cottage, #00949, Replace Roof,
2000 |
| 39 | | | Civil Engineering, CR119716, Replace East Lower/Upper
Roofs,
2000 |
| 40 | | | Coleman Hall, CR112951, Install Trash Chute Fire
Suppression System,
2000 |
| 41 | | | Doak Hall, CR092010,
2000 |
| 42 | | | Drane Hall, #00197, Annual Carpet-Repair Carpet Room
335,
2000 |
| 43 | | | Drane Hall, #00590, Renovation,
2000 |
| box | folder |
| 63 | 1 | | | Electrical Engineering, FP and C 96-43, Charles E.
Bassett II Pulse Lab Addition-Additional Work,
2000 |
| 2 | | | Engineering Center, #00898, Supply Air and Heat to
Hallway between Engineering Center and Petroleum Engineering,
2000 |
| 3 | | | Engineering Tech, #00813, Install RO Water,
2000 |
| 4 | | | English, #00871, Modify Elevator Controls to Meet ADA
Requirements,
2000 |
| 5 | | | English-Philosophy-Education, FP and C 96-36,
2000 |
| 6 | | | Fire Station and Credit Union, #00839, Install Gas
Line and Communication Conduit,
2000 |
| 7 | | | Food Tech, #01166, Paint Interior,
2000 |
| 8 | | | Foreign Language, #01219, Survey Tunnel Distances from
Foreign Language Building,
2000 |
| 9 | | | Goddard, #00820, Install Carpet,
2000 |
| 10 | | | Goddard and Plant Science, CR106679, Upgrade Lighting,
2000 |
| 11 | | | Goddard Range and Wildlife, #01217, Change Building
Name from Goddard Ranch to Wildlife Management,
2000 |
| 12 | | | Hazardous Waste Storage Facility, #01294, Replace
Roof,
2000 |
| 13 | | | Holden Hall, #00442, Carpet Room 242 (Furniture
also?),
2000 |
| 14 | | | Holden Hall, #01042, Assess best solutions for
preservation of the Peter Hurd Mural,
2000 |
| 15 | | | Holden Hall, #01149, Reupholster 5 chairs-room 203,
2000 |
| 16 | | | Holden Hall, #CR116407, Carpet Room 203,
2000 |
| 17 | | | Housing Services, #00005, Install Telephone Service to
Elevators,
2000 |
| 18 | | | Housing Services, #00738,
2000 |
| 19 | | | Human Sciences, #01037, Replace Exhaust System for
Fume Hood in Room 507,
2000 |
| 20 | | | Human Sciences, CR117527, Carpet Room 301-309,
311-312, 314, 316, 318, 320,
2000 |
| 21 | | | Human Sciences, CR120627, 2 Chairs room 281,
2000 |
| 22 | | | International Textile Center, #00197, Annual
Carpet-Repair carpet (W055376),
2000 |
| 23 | | | International Textile Center, #00788 Provide Air
Conditioning for Room 147,
2000 |
| 24 | | | Jones Stadium, #00196, Replace Storm Water Ejector
Pump,
2000 |
| 25 | | | Jones Stadium, #00278, Install Domestic Water Line,
2000 |
| 26 | | | Journalism, #00978, Add Air Conditioning,
2000 |
| 27 | | | Junctopm, CR120404 Remove Water Tank,
2000 |
| 28 | | | KTXT, #01331, Provide a DCC for adding a new front,
2000 |
| 29 | | | Landscape Architecture, CR120194, Update Electrical
System,
2000 |
| 30 | | | Law #00177, Supreme Court Benches,
2000 |
| 31 | | | Law #00918, Reupholster 4 sofas and ottomans,
2000 |
| 32 | | | Law, #01354, Expand 2 workstations,
2000 |
| 33 | | | Law, #01390, Convert Downtown Property into Law
Clinic,
2000 |
| 34 | | | Library, #00742, Renovate First Floor South Wing,
2000 |
| 35 | | | Maedgen Theatre, #00832, Annual Carpet-Replace Carpet
Room 106, 108, 110, 116, 120, 129, 130, 131, Lobby Corridors,
2000 |
| 36 | | | Mass Comm/Journalism, #01270, Research Structural
Integrity of Basement under the outside plaza,
2000 |
| 37 | | | Math, #01212, Lighting Retrofit in Vestibule,
2000 |
| 38 | | | Men's Gym, #00825, Develop New Classrooms,
2000 |
| 39 | | | Men's Gym, #00826, Develop 5 offices in room 210,
2000 |
| 40 | | | Men's Gym, #00827, Install Force Plate into floor of
basketball court,
2000 |
| 41 | | | Men's Gym, #00942, Improve Hallway Lighting,
2000 |
| 42 | | | Men's Gym, CR119718, Replace Roof,
2000 |
| 43 | | | Music, #00950, Investigate odors from basement sump
pit,
2000 |
| box | folder |
| 64 | 1 | | | Music, #00962, Evaluate Temperature Controls,
2000 |
| 2 | | | Music, #00982, Replace Jack in Elevator in 1,
2000 |
| 3 | | | Petroleum Engineering, #00817, Convert Room 204 to
Student Lounge,
2000 |
| 4 | | | Petroleum Engineering, #01119, Install Doors Outside
Room 211,
2000 |
| 5 | | | Physical Plant, #00330, Build Mezzanine, Central
Warehouse,
2000 |
| 6 | | | Physical Plant, #01199, Replace Air Conditioning Unit
at BMC Paint Shop with a DX Unit,
2000 |
| 7 | | | Physical Plant, #01290, Washington DC Condos,
2000 |
| 8 | | | Plant Sciences, #00947, Install Carpet Room 211A,
2000 |
| 9 | | | Psychology, #01035, Remodel Large Computer Room B-14
into small three rooms,
2000 |
| 10 | | | Psychology, CR119715, Replace Roof, 1 of 2,
2000 |
| 11 | | | Psychology, CR119715, Replace Roof, 2 of 2,
2000 |
| 12 | | | Ranching Heritage Center, #00920, Review Restrooms for
ADA,
2000 |
| 13 | | | Ranching Heritage Center, CR119648,
2000 |
| 14 | | | Ranching Heritage Center, CR120436, Replace carpet
room 103C, D and E,
2000 |
| 15 | | | Reese 250, #00540, Install Vacuum System,
2000 |
| 16 | | | Reese 250, CR120498, Repair Roof,
2000 |
| 17 | | | Reese 250/350, CR120501, Repair Floor Covering,
2000 |
| 18 | | | Reese 250/350, CR120678, Clean up/HVAC Start Up,
2000 |
| 19 | | | Reese 252, #00250, Construct a Bathroom,
2000 |
| 20 | | | Reese 460, #00787, Correct Problem of water in front
of rollup door in building 460,
2000 |
| 21 | | | Reese 552, #01145, Electrical Work Study,
2000 |
| 22 | | | Reese 555, CR120557, Provide Filters on Return/Make-Up
Air,
2000 |
| 23 | | | Reese Center, #00678, Electrical Power for Tower Site,
2000 |
| 24 | | | Science, #00430, Connect room 40 Fume Hood to Room 32
Stack,
2000 |
| 25 | | | Science, #00525, Evaluate Electrical System,
2000 |
| 26 | | | Science, CR093920, Install Laser Locking System,
2000 |
| 27 | | | Science, CR120254, Renovate 2nd Floor Restrooms,
2000 |
| 28 | | | Science, CR120541, Install Exhaust System in Book
Binding Area,
2000 |
| 29 | | | Science, CR120545, Install Window Shade-Room 234,
2000 |
| 30 | | | Science, CR120663, Renovate Room 326,
2000 |
| 31 | | | Student Rec Center, #00849, Add Smoke Detectors to
Elevator,
2000 |
| 32 | | | Student Rec Center, #00852, Rename the Student Rec
Center,
2000 |
| 33 | | | Student Rec Center, #01061, Repair Floor Tiles in
Showers,
2000 |
| 34 | | | Student Rec Center, #01273, Check Air Handler Unit,
2000 |
| 35 | | | Student Rec Center, CR084473, Automatic HVAC System,
2000 |
| 36 | | | Student Rec Center, CR119851, Replace Underwater
Lights in Pool,
2000 |
| 37 | | | Student Rec Center, CR120702, Renovate Room 202 and
203,
2000 |
| 38 | | | Student Rec Center, FP and C 98-20 Addition,
2000 |
| 39 | | | TTU Credit Union, #01311, Law Tunnel to West of
Indiana Ave.,
2000 |
| 40 | | | Tunnel System, CR117180, CHACP 1 to Biology,
2000 |
| 41 | | | Tunnels/EMS, CR120482, Conduit from CHACP 1 to Meats
Lab for Fiber Optic Cable,
2000 |
| 42 | | | United Spirit Arena, #00281, Install Direct-Buried
Interducts-men's gym to athletics dept. offices,
2000 |
| 43 | | | United Spirit Arena, #00291, Finish Work in Catering
Kitchen,
2000 |
| 44 | | | United Spirit Arena, #00432, Install Coiling Doors,
Event Level,
2000 |
| 45 | | | United Spirit Arena, #00515, Provide Platform for
Irrigation Booster Pump,
2000 |
| 46 | | | United Spirit Arena, Various, Construction of United
Spirit Arena,
2000 |
| 47 | | | University Center, #00042, Recover 12 Chairs,
2000 |
| 48 | | | University Center, CR092839, Renovate Cove Lighting at
Chick-Fil-A,
2000 |
| 49 | | | University Center, CR112484, Replace Sound
System-Allen Theatre,
2000 |
| 50 | | | University Plaza, #01489, Replace 4" Soil Sack above
2nd Floor,
2000 |
| 51 | | | University Theatre, FP and C 96-31, Reroof,
2000 |
| box | folder |
| 65 | 1 | | | University Theatre, #00596, Change Name to Charles E.
Maedgen Theatre,
2000 |
| 2 | | | UPD-University Police Department, #00456, Correct ADA
Deficiencies,
2000 |
| 3 | | | UPD-University Police Department Firing Range, #00805,
Renovate for Operations Dept. Move,
2000 |
| 4 | | | Wall Gates and Coleman Hall, CR116172, Elevator
Renovations, 1 of 2,
2000 |
| 5 | | | Wall/Gates and Coleman Hall, CR116172, Elevator
Renovations, 2 of 2,
2000 |
| 6 | | | West Hall, #00197, Annual Carpet-Replace Carpet-Rm
238, 240, 242, 244,
2000 |
| 7 | | | West Hall, #00232, Carpet 10 Rooms,
2000 |
| 8 | | | West Hall, #0300, Improve Lighting in Room 310,
2000 |
| 9 | | | West Hall, #00595, Renovate Room 205,
2000 |
| 10 | | | West Hall, #00744, Replace Carpet in Room 237,
2000 |
| 11 | | | West Hall, #00800, Install Additional Power and
Communications wireways for new furniture,
2000 |
| 12 | | | West Hall, #00843, Install Carpet in Room 257,
2000 |
| 13 | | | West Hall, #00877, Replace Carpet in Room 308,
2000 |
| 14 | | | West Hall, #01139, Remove Wall Between room 253 and
253A,
2000 |
| 15 | | | West Hall, #01407, New Furniture for Interview Room,
2000 |
| 16 | | | West Hall, CR119757, Add 6 Lights in Open Area, 1
light in room 259 and 2 lights in room 260,
2000 |
| 17 | | | West Hall, CR119959, Install New Carpet in room 241,
2000 |
| 18 | | | West Hall, CR120457, Carpet Room 335,
2000 |
| 19 | | | West Hall, Carpet In Rm 226,
2000 |
| 20 | | | West Hall, None, Carpet Repairs,
2000 |
| 21 | | | Weymouth/Chitwood Hall, CR119847, Replace Hot Water
Heaters,
2000 |
| 22 | | | Women's Gym, #00824, Construct Undergraduate
Laboratory and Classroom Space,
2000 |
| 23 | | | Administrative Support Center, #01327, Renovate Room
103,
2000 |
| 24 | | | Administrative Support Center, #01660, Tint Windows
room 145,
2000 |
| 25 | | | Administrative Support Center, #01737, Convert room
119 into 2 offices,
2001 |
| 26 | | | Administrative Support Center, #01865, Install Exhaust
Fan-Room 145,
2001 |
| 27 | | | Administrative Support Center, #01982, Install Heat
pump in room 101n,
2001 |
| 28 | | | Administrative Support Center, #02028 Divide Room
101J-A into 3 offices,
2001 |
| 29 | | | Administrative Support Center, #02152, Space Planning
Offices,
2001 |
| 30 | | | Administration, #01176, Mini-Blinds for Room 213,
2001 |
| 31 | | | Administration, #01259, Blackout drapes, Teacher
Podium Spectrum,
2001 |
| 32 | | | Administration, #01531, Install Panic Button in
President's Suite,
2000 |
| 33 | | | Ag Ed and Communications, #01325, Repair Carpet,
2001 |
| 34 | | | Ag Ed and Communications, #01645, Renovate 2nd Floor,
2001 |
| 35 | | | Ag Pavilion, #02000, Install Exhaust Vent in Room 102,
2001 |
| 36 | | | Ag Sciences, #00087, Renovate room 202, 308, 311,
2001 |
| 37 | | | Ag Sciences, #00197, Annual Carpet-Repair Loose Carpet
in Room 102,
2001 |
| 38 | | | Ag Sciences, #01109, Room 302-Curtains, dimmers,
furniture,
2001 |
| 39 | | | Ag Sciences, #01133, Black out Curtains, Lighting, and
fixed seating,
2001 |
| 40 | | | Ag Sciences, #01907, Annual carpet-replace carpet room
313,
2001 |
| 41 | | | Animal Science, #01714, Mini-Blinds,
2001 |
| 42 | | | Animal Science, #01907, Annual Carpet,
2001 |
| 43 | | | Aquatic Center, #01735, Recarpet office,
2001 |
| 44 | | | Architecture, #00708, Upgrade Electrical System,
2001 |
| 45 | | | Architecture, #01024, Recushion chairs and reupholster
chairs,
2001 |
| 46 | | | Architecture, #01174, Install aluminum store front
door,
2001 |
| 47 | | | Architecture, W00076958,
2001 |
| 48 | | | Athletic Kit and Dining, #01956, Repair Roof,
2001 |
| 49 | | | Athletic Training Center, #01761, Hang/Install
scoreboard in ATC,
2001 |
| 50 | | | Biology, #01907, Annual Carpet,
2001 |
| 51 | | | Biology Greenhouse, #01513, Install drip pans on plant
tables,
2001 |
| 52 | | | Bookstore, #00642, Replace Roof,
2001 |
| 53 | | | Business Administration, #01542, Carpet-Room 507,
2000 |
| 54 | | | Business Administration, #01543, Carpet-Room 811,
2001 |
| 55 | | | Business Administration, #01554, Covert Lab (164) into
office space for Stephenson Chair holder and new research center,
2001 |
| 56 | | | Business Adminstration, #01784, Paint Room 152,
2001 |
| 57 | | | Business Adminstration, CR116632, Campus Buildings
Interior Painting-Phase 4, 1 of 2,
2001 |
| 58 | | | Business Administration, CR116632, Campus Buildings
Interior Painting-Phase 4, 2 of 2,
2001 |
| 59 | | | Campus Area Systems, #02134, RFQ Haz. Mat. Removal,
2001 |
| 60 | | | Campus Carpet, W0052913, Replace Carpet in room 168
Drane Hall,
2001 |
| 61 | | | Campus E and G, #01518, Fixed and Moveable classroom
seating,
2001 |
| 62 | | | Campus E and G, #01647, Replace Annual Moveable
Furniture for Psychology, Human Sciences, Foreign Languages, Women's Gym, and
B.A.,
2001 |
| 63 | | | Campus Elevators, #00743, FY00 Upgrade Elevators-Phase
VI,
2001 |
| box | folder |
| 66 | 1 | | | Campus Elevators, #01802, FY00 Safety Inspection for E
and G Bldgs,
2001 |
| 2 | | | Campus Elevators, Various, FY00 Service Callbacks not
covered by service Maintenance Contract,
2001 |
| 3 | | | Campus Roof Repair, #00511, Roof Repairs,
2001 |
| 4 | | | Campus Tunnel System-Wiggins, CR096841, Upgrade Energy
Management System, 1 of 2,
2001 |
| 5 | | | Campus Tunnel System-Wiggins, CR096841, Upgrade Energy
Management System,
2001 |
| 6 | | | CHACP, 00148, Prepare area for safety office,
2001 |
| 7 | | | CHACP 1, #01685, Redesign Safety Fleet Office,
2001 |
| 8 | | | CHACP 2, #01072, Steam Pipe Noise,
2001 |
| 9 | | | CHACP 2, #01223, Construct Mezzanine for Instrument
Shop,
2001 |
| 10 | | | CHACP 2, #01401, Carpet room 202, 203, 204, 205,
2001 |
| 11 | | | CHACP 2, #01534, Review Isolation Breaker,
2001 |
| 12 | | | CHACP 2, #015-63, FY01 Safety Insp., SVC. Contr.
Service and Administrative Costs,
2001 |
| 13 | | | Chemical Engineering, #01288, Reinstall 10 Lab Benches
in Room 104,
2001 |
| 14 | | | Chemical Engineering, #01396, Install Remaining
Cabinets in Room 104,
2001 |
| 15 | | | Chemical Engineering, CR120604, Renovate rooms
201/202,
2001 |
| 16 | | | Chemistry, #01185, Install Optical Eye on elevator
door for ADA,
2001 |
| 17 | | | Chemistry, #01376, Perform Preventative Maintenance on
Two Pringle switches,
2001 |
| 18 | | | Chemistry #01682, Convert Room 407A into plant growth
room,
2001 |
| 19 | | | Chemistry #01799, Repair Fire Damage,
2001 |
| 20 | | | Dan Law Field, #01699, FY01 Elevator Costs,
2001 |
| 21 | | | Doak Hall, W0066004, Carpet Repairs,
2001 |
| 22 | | | Drane Hall, #00807, Renovate Accounting Services room
201, 206, 211, 213, 215, 215a,
2001 |
| 23 | | | Drane Hall, #00924, Phase 10-Renovate Room 352, 354,
357, 359, 361, 363,
2001 |
| 24 | | | Drane Hall, #01078, Cover Existing door in room 163C,
2001 |
| 25 | | | Drane Hall, #01526, Repair Carpet-Room163C,
2001 |
| 26 | | | Drane Hall, #01702, Furniture for Room 330,
2001 |
| 27 | | | Drane Hall, CR120261, Furniture for Room 143-Phase 6,
2001 |
| 28 | | | Engineering Center, #01907, Annual Carpet-Replace
Carpet Rooms 101 thru 106; 109 thru 111 and corridor,
2001 |
| 29 | | | Engineering Center, #01924, Maintain Room 111 at 60
degrees,
2001 |
| 30 | | | English, #00559, Replace Roof,
2000 |
| 31 | | | Erskine Farm, #01791, Determine if 3 phase (440)
Electrical capacity is available in building,
2001 |
| 32 | | | Erskine Warehouse, #00151, Replace Roofs,
2001 |
| 33 | | | Food Tech, #01665, New Carpeting in offices and
conference room,
2001 |
| 34 | | | Foreign Languages, #01184, Structural problems in
basement courtyard,
2001 |
| 35 | | | Goddard Range and Wildlife, #00821, Replace Fixed
seating in room 101,
2001 |
| 36 | | | Goddard Range and Wildlife, #01770, Determine
structural integrity of flooring in the lecture hall,
2001 |
| 37 | | | Grantham, #00872, Renovate HVAC System,
2001 |
| 38 | | | Hazardous Chemical Storage, #01921, Upgrade Heating
System,
2001 |
| 39 | | | Health Science Center, #01233, Assess Fiber Optic
cable installation from HSC DEMARC to Sears Methodist teaching nursing home
north of 4th St.,
2001 |
| 40 | | | Holden Hall, #00831, Renovate area for Dr. Haragan's
Office Room 205/206,
2001 |
| 41 | | | Holden Hall, #01124, Convert Room 208, 209 into
offices,
2001 |
| 42 | | | Holden Hall, #013505, Electrical Work for 2 person
workstation,
2001 |
| 43 | | | Holden Hall, #01441, Provide Space for Student
Assistant,
2001 |
| 44 | | | Holden Hall, #01587, Carpet Room 38,
2001 |
| 45 | | | Holden Hall, #01619, Install mini-blinds in room 036E,
2001 |
| 46 | | | Holden Hall, #01757, Install a door and extend walls
in suite 103,
2001 |
| 47 | | | Holden Hall, #01760, Design studiese room 79,
2001 |
| 48 | | | Holden Hall, #01764, Install angled baffles,
2001 |
| 49 | | | Holden Hall, #01771, Remodel Old Faculty Senate Room,
2001 |
| 50 | | | Holden Hall, #01789, Evaluate Electrical outlets in
room 108,
2001 |
| 51 | | | Holden Hall, CR120302, Coil Replacement for A/H 7 and
8,
2001 |
| box | folder |
| 67 | 1 | | | Housing Services, #00470, Repair dampers in A/C heat
ductwork for laundry rooms in Hulen/Clement and Wall/Gates,
2001 |
| 2 | | | Housing Services, #00738, FY00 Code Deficiency
Corrections,
2001 |
| 3 | | | Housing Services, #01600, FY01 Administrative Costs,
2001 |
| 4 | | | Human Sciences, #00197, Annual Carpet-Repair Carpet
Room 257 and 259,
2001 |
| 5 | | | Human Sciences, #00888, Renovate El Centro and Canyon
Rooms,
2001 |
| 6 | | | Human Sciecnes, #00954, Interior Painting,
2001 |
| 7 | | | Human Sciences, #01068, Carpet in room 103B,
2001 |
| 8 | | | Human Sciences, #01096, Various Renovations,
2001 |
| 9 | | | I.T.C. International Textile Center, #01144, Remodel
Lab-Evaluate IAQ room 143, 145,
2001 |
| 10 | | | International Cultural Center. #01560, FY01
Administrative Costs,
2001 |
| 11 | | | Jones Stadium, #00837, Football Practice Field
Lighting,
2001 |
| 12 | | | Jones Stadium, #01698, FY01 Elevator Costs,
2001 |
| 13 | | | Journalism, #00197, Annual Carpet-Repair Carpet main
entrance room 103,
2001 |
| 14 | | | Journalism, #01298, Renovate room 6,
2001 |
| 15 | | | KTXT TV, #00221, Replace Roof,
2001 |
| 16 | | | KTXT TV #01330, Provide a DCC to eliminate noise
problems,
2001 |
| 17 | | | KTXT TV, #01468, Repair electrical grounding in
building,
2001 |
| 18 | | | Law, #01347, Wiring for video and computer
equipment-room 106, 107, 201-203,
2001 |
| 19 | | | Law, #01406, Repair carpet room 127,
2001 |
| 20 | | | Law, #01750, Surveillance camera-Law Library room 125,
2001 |
| 21 | | | Law, #01824, Interior finishes for 3rd floor offices,
2001 |
| 22 | | | Law, #01966, Replace Carpet Tiles,
2001 |
| 23 | | | Library, #01335, New Circuits and Receptacles,
2001 |
| 24 | | | Library, #01880, Carpet Room 76,
2001 |
| 25 | | | Library, #02081, Library Floor Load Study,
2001 |
| 26 | | | Library, CR094843, Carpet V-1 ATLC Renovation,
2001 |
| 27 | | | Library, CR120441, Phase 2-Room Partitions,
2001 |
| 28 | | | Lubbock Lake Landmark, #01730, Electrical Code Upgrade
for Exhibit Galleries,
2001 |
| 29 | | | Lubbock Lake Landmark, #01731, Electrical
Inspection-Field Campus and Research Facilities,
2001 |
| 30 | | | Mathematical Sciences, CR120032, Renovate Vacated
Southwest Collections Area,
2001 |
| 31 | | | McClellan Hall, #01926, Create offices for 5 people,
2001 |
| 32 | | | McClellan Hall, #02130, Carpet/Paint Room 101,
2001 |
| 33 | | | McClellan Hall, #02131, Move Testing carrels to room
101,
2001 |
| 34 | | | McClellan Hall, #02132, 1st Floor Bathroom ADA,
2001 |
| 35 | | | Meats Lab, #00158, Add Walls and Cabinet bench room
110,
2001 |
| 36 | | | Meats Lab, #01132, Repair Fire Damage,
2001 |
| 37 | | | Mechanical Engineering, #01577, Add Electrical service
for equipment at north side of wind tunnel,
2001 |
| 38 | | | Mechanical Engineering, #01705, Connect 220V, 30
Electrical Power to HAAS Horizontal CNC machine,
2001 |
| 39 | | | Mechanical Engineering, #01853, Feasibility of
Additional Ventilation for ammonia desiccant heat exchanger in room 120,
2001 |
| 40 | | | Mechanical Engineering, #01854, Hallway lighting and
lenses,
2001 |
| 41 | | | Mechanical Engineering, #01855, Improve Seating in
room 142, 146, and 149,
2001 |
| 42 | | | Men's Gym, #00651, HVAC Renovation,
2001 |
| box | folder |
| 68 | 1 | | | Museum, #01040, Main Gallery Lighting Upgrade,
2001 |
| 2 | | | Museum, #01229, Rework Switches in the Gallery,
2001 |
| 3 | | | Museum, CR120440, Convert 1st Floor Restroom for ADA,
2001 |
| 4 | | | Music, #00832, Annual Carpet-Replace Carpet Room 8 and
9,
2001 |
| 5 | | | Music, #00961, Determine if new breaker is needed,
2001 |
| 6 | | | Music, #01189, Enclose area under Mezzanine,
2001 |
| 7 | | | Music, #01462, Install ventilation system in west
basement mechanical room below 107 and 108,
2001 |
| 8 | | | Music, Cr 120638, Replace EMS System,
2001 |
| 9 | | | Music/University Center, CR116079, Replace Fire Alarm
System,
2001 |
| 10 | | | National Ranching Heritage, #01519, Upgrade of the
Brush Arbor area,
2001 |
| 11 | | | Petroleum Engineering, #00975, Interior Painting and
Signage,
2001 |
| 12 | | | Petroleum Engineering, #01402, Student Resource Center
being refurbished by SPE,
2001 |
| 13 | | | Petroleum Engineering, #01933, Repair Carpet,
2001 |
| 14 | | | Petroleum Engineering, #01934, Return Air Study,
2001 |
| 15 | | | Petroleum Engineering, #02049, Replace Andover System,
2001 |
| 16 | | | Petroleum Engineering, #02127, Electrical/duct
work-room III,
2001 |
| 17 | | | Petroleum Engineering, #02166, Wiring for ovens-room
III,
2001 |
| 18 | | | Physical Plant, #00511, Repair Roof on Garage,
2001 |
| 19 | | | Physical Plant, #00811, Exterior Signage,
2001 |
| 20 | | | Physical Plant, #01022, Renovate room 112,
2001 |
| 21 | | | Physical Plant, #01069, Modify room 105-Human
Resources,
2001 |
| 22 | | | Physical Plant, #01198, Construct Partition in room
103,
2001 |
| 23 | | | Physical Plant, #01527, Fiber Optic Cable,
2001 |
| 24 | | | Physical Plant, #01571, Install carpet room 103A,
2001 |
| 25 | | | Physical Plant, #01697, Purchase surplus carpet for
storage in central warehouse,
2001 |
| 26 | | | Physical Plant, #01762, Install power logic meter,
etc,
2001 |
| 27 | | | Physical Plant, #01812, Work Table Room 104,
2001 |
| 28 | | | Physical Plant, #01895, Install Cooling Systems,
2001 |
| 29 | | | Plant Sciences, #00812, Replace Roof,
2001 |
| 30 | | | Plant Sciences, #01130, Renovate Room 115 as a
multi-media conference room,
2001 |
| 31 | | | PrinTech, #00880, Renovate Building for new
publications center,
2001 |
| 32 | | | PrinTech, #00894, Replace Lower Roofs,
2001 |
| 33 | | | PrinTech, #01637, Repair/clean/replace HVAC coils,
chilled water valves, pumps and temperature controls,
2001 |
| 34 | | | PrinTech, #02079, Heat Build up in the server room,
2001 |
| 35 | | | Psychology, #01671, Install Roller shades room 301,
2001 |
| 36 | | | Psychology, #01950, Improve Lighting,
2001 |
| 37 | | | Psychology, #01959, Return Air Study,
2001 |
| 38 | | | Psychology, #01960, Modify smoking room,
2001 |
| 39 | | | Psychology, #01961, Repair Carpet in room 114, 117H,
212, 207, 201,
2001 |
| 40 | | | Psychology, #02078, Carpet Room 115 and 113,
2001 |
| 41 | | | Ranching Heritage Center, #01230, Install New lights
and ceiling fans-Burns pavillion,
2001 |
| 42 | | | Ranching Heritage Center, CR108778, Paint Exterior,
2001 |
| 43 | | | Ranching Heritage Center, CR119648, Replace Roof,
2001 |
| 44 | | | Recreation Center, #00985, Renovate Suites 202 and
203,
2001 |
| 45 | | | Recreation Center, #01177, Raquetball Court
Resurfacing,
2001 |
| 46 | | | Recreation Center, #01561, FY01 Elevator Safety
Inspection Administration, Service Contract Costs,
2001 |
| box | folder |
| 69 | 1 | | | Recreation Center, #01599, Repair Roof, 1 of 2,
2001 |
| 2 | | | Recreation Center, #01599, Repair Roof, 10 prints, 2
of 2,
2001 |
| 3 | | | Recreation Center, #01625, Synthetic Overpour on
Basketball Court #5,
2001 |
| 4 | | | Recreation Center, #01689, Exterior Signage,
2001 |
| 5 | | | Reese Center, #01469, Space Planning and Furniture for
HPCC building 555,
2001 |
| 6 | | | Reese Center, #01504, Install a thimble connection on
the 2 biological safety cabinets,
2001 |
| 7 | | | Reese Center, #01783, Install Antennas,
2001 |
| 8 | | | Reese Center, #01922, Power Consumption Study,
2001 |
| 9 | | | Reese Center, WO 050425, Renovate Building 250 for
WERC,
2001 |
| 10 | | | Science, #00039, Safety Cabinet for X-Ray diffraction
unit,
2001 |
| 11 | | | Sneed/Weeks, #01261, Size and run power to 2 wells at
Sneed and at Weeks,
2001 |
| 12 | | | Southwest Campus, #01517, Purchase 35 new filing
cabinets for the outreach and extended studies Dept. at 6901 Quaker Ave.,
2001 |
| 13 | | | Southwest Collection/ Special Collections Library,
#02247, Furniture Room 113/117,
2001 |
| 14 | | | Stangel Hall, #01515, Replace Chill Water Coils and
valves on air handler 9 and 10,
2001 |
| 15 | | | Texas Instruments, #01965, Demolition Plan,
2001 |
| 16 | | | Texas Tech House, #01655, Modify closets in SW corner
of east wing into restroom facility,
2001 |
| 17 | | | Texas Tech House, #01787, Install Removable tent
system for courtyard area at Chancellor's Residence,
2001 |
| 18 | | | Texas Tech Tow Yard, #01551, Get Electricity to
storage building,
2001 |
| 19 | | | United Spirit Arena, #01688, FY01 Elevator Costs,
2001 |
| 20 | | | University Center, #00524, Provide Elevator
Blueprints,
2001 |
| 21 | | | University Center, #01687, FY01 Elevator Costs,
2001 |
| 22 | | | University Center, #01741, Drapes for room 203,
2001 |
| 23 | | | University Center, CR119720, Renovate Faculty Club,
2001 |
| 24 | | | University Plaza, #01490, Install Grill and filters on
outside air makeup for the air handler,
2001 |
| 25 | | | University Plaza, #01491, Repair/replace roof drain
systems on NW side of bldg.,
2001 |
| 26 | | | University Plaza, #01627, Emergency Lighting,
2001 |
| 27 | | | University Plaza, #01920, Carpet Room 520A and 5350A,
2001 |
| 28 | | | University Plaza, #02036, Carpet Room 403B,
2001 |
| 29 | | | University Theatre, #00719, Upgrade Powere for new
dinner,
2001 |
| 30 | | | University Theatre, #01598, Install Spray Booth,
2001 |
| 31 | | | West Hall, #00197, Annual Carpet-Replace carpet room
305-308 and 311,
2001 |
| 32 | | | West Hall, #00832, Annual Carpet-Replace carpet room
206, 208, 210, 212,
2001 |
| 33 | | | West Hall, #00921, Mini blinds in student financial
aid room 310,
2001 |
| 34 | | | West Hall, #00947, Carpet in Financial Aid Office room
305 thru 332,
2001 |
| 35 | | | West Hall, #01423, Mini Blinds in room 237,
2001 |
| 36 | | | West Hall, #01892, Renovate room 241,
2001 |
| 37 | | | West Hall, CR120481, Replace Carpet Room 237,
2001 |
| 38 | | | Administration Support Center, #01327, Renovate room
103,
2002 |
| 39 | | | Administrative Support Center, #02008, Recarpet room
127,
2002 |
| 40 | | | Administrative Support Center, #02056, Venetian Blinds
between room 203 and 204,
2002 |
| 41 | | | Administrative Support Center, #02151, Furniture
Moves,
2002 |
| 42 | | | Administative Support Center, #02476, New Tables and
chairs for conference room 106,
2002 |
| 43 | | | Administrative Support Center, #02742, New work
station for reception area,
2002 |
| 44 | | | Administration, #01437, Furniture for Mr. Wilson's
office, suite 150,
2002 |
| 45 | | | Administration, #01579, Replace Existing Elevator,
2002 |
| 46 | | | Administration, #02061, New Furniture room 150,
2002 |
| 47 | | | Administration, #02112, A/H #7 Upgrade,
2002 |
| 48 | | | Administration, #02212, Furniture for room 161,
2002 |
| 49 | | | Administration, #02256, Carpet Room 213,
2002 |
| 50 | | | Administration, #02433, Furniture for new 12x14 Space
Within room 304,
2002 |
| 51 | | | Administration, WO 100127, Carpet southwest entrance,
2002 |
| 52 | | | Administration, WO107774, Carpet Loose,
2002 |
| 53 | | | Ad Ed and Communications, #01235, Upgrade Restrooms,
2002 |
| 54 | | | Ag Ed and Communications, #01421, Recarpet room 103,
103a, 105, 109, 202, 207, 214, 206,
2002 |
| 55 | | | Ag Ed and Communications, #02065, Carpet Room 207 and
206,
2002 |
| 56 | | | Ag Ed and Communications, #02066, Renovate Room 100,
2002 |
| 57 | | | Ag Ed and Communications, WO104287, Repair Loose
carpet in room 106,
2002 |
| 58 | | | Ag Plant Science, #01985, Renovate room 108,
2002 |
| 59 | | | Ag Plant Science, #02295, Update room 110,
2002 |
| 60 | | | Ag Plant Science, #02296, Update room 113,
2002 |
| 61 | | | Ag Plant Science, #02358, Remodel room 209,
2002 |
| 62 | | | Ag Plant Science, FY02-26, Demolish room 214 prior to
renovation,
2002 |
| 63 | | | Ag Sciences, #01034, Renovate room 311,
2002 |
| 64 | | | Ag Sciences, #01141, Renovate Room 206 and 208,
2002 |
| 65 | | | Ag Sciences, #01193, Renovate room 205A,
2002 |
| box | folder |
| 70 | 1 | | | Ag Sciences, #01635, Replace Roof,
2002 |
| 2 | | | Ag Sciences, #02002, Concept design for 3rd floor
hallways,
2002 |
| 3 | | | Ag Sciences, #02421, mini blinds room 218,
2002 |
| 4 | | | Ag Sciences, WO031510, Renovate room 205,
2002 |
| 5 | | | Ag Sciences, WO090776, Repair carpet room 301,
2002 |
| 6 | | | Ag Sciences, WO102235, Repair Carpet room 311,
2002 |
| 7 | | | Agriculture Pavilion, #01874, Remove Wall between room
201 and 202,
2002 |
| 8 | | | Agriculture Pavilion, #02349, Interior Lighting,
2002 |
| 9 | | | Agriculture Pavilion, #02699, Replace HVAC System,
2002 |
| 10 | | | Animal Science, #02544, Carpet Room 116,
2002 |
| 11 | | | Aquatic Center, #01408, Replace Pool recirculation
piping,
2002 |
| 12 | | | Aquatic Center, #02426, Upgrade Electrical Circuits,
2002 |
| 13 | | | Architecture, #00152, Replace Roof, 1 of 2,
2002 |
| 14 | | | Architecture, #00152, Replace Roof,
2002 |
| 15 | | | Architecture, #00893, Renovate Studio,
2002 |
| 16 | | | Architecture, #01947, Modify 10th Floor restroom,
2002 |
| 17 | | | Architecture, #02339, Renovate Room 504,
2002 |
| 18 | | | Architecture, #02497, Renovate Room 902,
2002 |
| 19 | | | Architecture, #02564, Disassemble Booths,
2002 |
| 20 | | | Architecture, #02565, Weatherproof cover,
2002 |
| 21 | | | Art, #00832, Annual Carpet-Restretch carpet in room
101c,
2002 |
| 22 | | | Art, #01837, Campus Elevators-Smoke Detectors,
2002 |
| 23 | | | Art, #02084, Art Relocation/Renovate Central Foods
Warehouse,
2002 |
| 24 | | | Athletic Kitchen and Dining, #02321, Upgrade Computer
Lab,
2002 |
| 25 | | | Athletic Services, #02369, Softball/Tennis Signage,
2002 |
| 26 | | | Athletic Training Center, #01572, Repair/Replace
outside air lock door,
2002 |
| 27 | | | Biology, #01634, Reroof Clay Tile Roof,
2002 |
| 28 | | | Biology, #01834, Campus Elevators-Elevator #4 Fire
Service,
2002 |
| 29 | | | Biology, #01952, Replace Fixed Seating,
2002 |
| 30 | | | Biology Greenhouse, #02490, Room 123 Heater,
2002 |
| 31 | | | Business Administration, #00294, Engrave Granite Wall,
2002 |
| 32 | | | Business Administration, #00717, Renovate Room 914,
2002 |
| 33 | | | Business Administration, #01200, Repair Exterior, 1 of
2,
2002 |
| 34 | | | Business Administration, #01200 Repair Exterior, 2 of
2,
2002 |
| 35 | | | Business Administration, #01308, Build Wall and
Install Carpet,
2002 |
| 36 | | | Business Administration, #01329, Repair and Repaint
Rotunda Exterior,
2002 |
| 37 | | | Business Administration, #01836, Lower Elevator
Buttons to ADA Height,
2002 |
| box | folder |
| 71 | 1 | | | Business Administration, #01907, Annual Carpet-Repair
room 306-308,
2002 |
| 2 | | | Business Administration, #02602, Install Horn/Strobes,
2002 |
| 3 | | | Business Administration, #01837-09 Fire Exting
wisher-elevator 1,
2002 |
| 4 | | | Business Administration, #01837-15, A/C
Duct/Register-Elevator Equipment Room,
2002 |
| 5 | | | Business Administration, WO92048, Repair carpet room
306,
2002 |
| 6 | | | Business Administration, WO101318, Restretch Carpet
room 814 and 405,
2002 |
| 7 | | | Business Administration, WO101319, Restretch carpet in
room 158,
2002 |
| 8 | | | Business Administration, WO106024, Repair loose carpet
room 114 and 614,
2002 |
| 9 | | | Campus Area Systems, #01773, Campus TechEvents
Computer/Monitors,
2002 |
| 10 | | | Campus Elevators, #01503, FY-01 E and G Elevator Call
backs for items not covered under service contact,
2002 |
| 11 | | | Campus Elevators, #01837, Campus Elevators-bring
campus elevators into compliance with NEC,
2002 |
| 12 | | | Campus Emergency Power, #01050, Emergency Power for
Traffic Signals,
2002 |
| 13 | | | Campus Exterior Lighting, #00966, Electrical Service
to Area Lights on Main Street,
2002 |
| 14 | | | Campus Exterior Lighting, #01951, Security Survey,
2002 |
| 15 | | | Campus Exterior Lighting, #02458, Relocate Intramural
Rec Field Light Switches,
2002 |
| 16 | | | Campus Tunnel Lighting, #01502, Replace Incandescent
Lights with Florescent,
2002 |
| 17 | | | Campus Utilities, #01113, Storm Sewer System, Dry Well
for Roof Drain,
2002 |
| 18 | | | CHACP1, #00808, Cabinet for Room 209,
2002 |
| 19 | | | CHACP1, #02547, Remodel 203,
2002 |
| 20 | | | CHACP1, WO208152, 2002 Maintenance Shutdown,
2002 |
| 21 | | | CHACP2, #01533, Upgrade Elevator,
2002 |
| 22 | | | Chemical Engineering, #01906, Self help install new
480v Equipment Circuit,
2002 |
| 23 | | | Chemical Engineering, #02097, Evaluate ARCO Room,
2002 |
| 24 | | | Chemical Engineering, #02769, Carpet room 201,
2002 |
| 25 | | | Chemistry, #01601, Install Laser Interlocks in room
132,
2002 |
| 26 | | | Chemistry, #01602, Install Laser Interlocks in room
329,
2002 |
| 27 | | | Chemistry, #01603, Install Laser Interlocks in room
332,
2002 |
| 28 | | | Chemistry, #01715, Install Laser Interlocks in room
331,
2002 |
| 29 | | | Chemistry, #01868, Install Carpet in room 049A,
2002 |
| 30 | | | Chemistry, #01890, Install Laser Interlocks in room
12,
2002 |
| 31 | | | Chemistry, #01894, Secondary CW Pump,
2002 |
| 32 | | | Chemistry, #02586, Remodel Room 038,
2002 |
| 33 | | | Chemistry, #02814, Install Lockable Cabinets in room
49 and 107,
2002 |
| 34 | | | Child Development, #01833, ADA Renovation of Restroom,
2002 |
| 35 | | | Chitwood Hall, #02317, Replace AHU Coils,
2002 |
| 36 | | | Civil Engineering, #01209, Install Vent and provide
make up air in room 182,
2002 |
| 37 | | | Civil Engineering, #01837, Campus Elevators to bring
in compliance with NEC,
2002 |
| 38 | | | Civil Engineering, #02412, Change out electrical
boxes,
2002 |
| 39 | | | Civil Engineering, #106569, Repair carpet room 205,
2002 |
| 40 | | | Computer Center, #02311, Upgrade Leibert,
2002 |
| 41 | | | Computer Center, #02517, Replace Carpet,
2002 |
| 42 | | | Drane Hall, #00702, Phase 6 Renovations,
2002 |
| 43 | | | Drane Hall, #01999, Carpet Room 163,
2002 |
| 44 | | | Drane Hall, #02058, Electrical Discrepancies,
2002 |
| 45 | | | Drane Hall, #02835, Recarpet and paint room 260, 262,
and 263,
2002 |
| 46 | | | Electrical Engineering, #01216, Construction of an
explosive facility,
2002 |
| 47 | | | Electrical Engineering, #092375, Repair carpet room
117, 118, 122,
2002 |
| 48 | | | Engineering Center, #00397, Replace 3 Leibert Air
Handlers,
2002 |
| 49 | | | Engineering Center, #00781, Exterior tile replacement,
2002 |
| 50 | | | Engineering Center, #01907, Annual Carpet Replacement,
2002 |
| 51 | | | Engineering Center, #02524, Furniture and Carpet 3rd
Floor,
2002 |
| 52 | | | Engineering Center, #02758, , Convert Conference Room
to Classroom,
2002 |
| 53 | | | Engineering Tech; #02725, Convert Lab into Conference
Room,
2002 |
| 54 | | | Foreign Language, #01779, Furniture for room 16, 18,
20,
2002 |
| 55 | | | Foreign Language, #02650, Renovate Room 18, 20,
2002 |
| 56 | | | Foreign Language, #02651, Recarpet Room 18,
2002 |
| 57 | | | Fuller Track, #01007, Install Lighting,
2002 |
| 58 | | | Gaston Hall, #02316, Replace AHU Coils,
2002 |
| 59 | | | Gates Hall, #02573, Abate and Check mold,
2002 |
| 60 | | | Goddard Range and Wildlife, #01837, Bring E and G
Elevators into compliance with the NEC,
2002 |
| 61 | | | Goddard Range and Wildlife #02192, Two Electric
Sockets in room 108M,
2002 |
| 62 | | | Goddard Range and Wildlife, #02197, Examine Walk-In
Freezer,
2002 |
| 63 | | | Golf Course, #02916, Design Porch for Golf Course
Building,
2002 |
| 64 | | | Grantham, #00979, Improve Air Circulation in room
109B,
2002 |
| 65 | | | Grantham, #01427, Estimate cost to reroof in stages,
2002 |
| 66 | | | Grantham, #01465, Exterior Paint,
2002 |
| 67 | | | Grantham, #02464, 40'x95' Metal Building with Office
Space,
2002 |
| box | folder |
| 72 | 1 | | | Holden Hall, #00404, Replace dome lighting, repair
plaster and repaint,
2002 |
| 2 | | | Holden Hall, #01121, Replace Interior Lighting,
2002 |
| 3 | | | Holden Hall, #01605, Install additional circuits and
walls in room 79,
2002 |
| 4 | | | Holden Hall, #01763, Charge Lettering,
2002 |
| 5 | | | Holden Hall, #01907, Annual Carpet-Replace carpet room
239, 79, 78,
2002 |
| 6 | | | Holden Hall, #02161, Remodel room 203E,
2002 |
| 7 | | | Holden Hall, #02445, Multimedia Upgrades, room 75, 76,
77,
2002 |
| 8 | | | Holden Hall, #02744, Enclose South Entrance of 107 for
an office,
2002 |
| 9 | | | Holden Hall, #02768, Vertical Blinds for room 40,
2002 |
| 10 | | | Holden Hall, W0106056, Repair Carpet tile in room 79,
2002 |
| 11 | | | Housing Services, #01879, Banging Pipes,
2002 |
| 12 | | | Human Sciences, #01186, Renovate room 104, 105, 106,
2002 |
| 13 | | | Human Sciences, #01227, Space Planning-reconfigure
room 136,
2002 |
| 14 | | | Human Sciences, #01673, Furniture for Office Area,
2002 |
| 15 | | | Human Sciences, #02183, Carpet Room 280,
2002 |
| 16 | | | Jones Stadium, #02302, Replace Carpet in corridor of
President's box and 2 offices,
2002 |
| 17 | | | Jounalism, #01907, Annual Carpet Replacement,
2002 |
| 18 | | | Journalism, #02403, Signage for name change to
"student media",
2002 |
| 19 | | | Junction Center, #01438, Renovate Bathhouse, 1 of 2,
2002 |
| 20 | | | Junction Center, #01438, Renovate Bathhouse, 2 of 2,
2002 |
| 21 | | | KTXT TV, #00378, Upgrade AC System,
2002 |
| 22 | | | KTXT-TV, #01332, Convert Restrooms to Storage Area,
2002 |
| 23 | | | KTXT TV, #01830, Furniture for room 101,
2002 |
| 24 | | | Law, #00689, Renovate First Floor Restroom,
2002 |
| 25 | | | Law, #01188, Renovate faculty library on 3rd floor,
2002 |
| 26 | | | Law, #01348, Renovate room 128,
2002 |
| 27 | | | Law, #01349, Renovate room 223,
2002 |
| 28 | | | Law, #01823, New Lighting for 3rd floor hallway and
office,
2002 |
| 29 | | | Law, #01967, Furniture for room 129,
2002 |
| 30 | | | Law, #01990, Upgrade Lighting,
2002 |
| 31 | | | Law, #02270, Install Carpet in lower basement,
2002 |
| 32 | | | Law, #02523, Carpet under shelves in law library,
2002 |
| 33 | | | Law, #02716, Carpet Room 128A,
2002 |
| 34 | | | Law, WO 067280, Repair torn carpet at entrance to room
108N,
2002 |
| 35 | | | Library, #00994, Modify 4 doors for compliance with
safety codes,
2002 |
| 36 | | | Library, #01706, ACS Room 32 Renovation,
2002 |
| 37 | | | Library, #01740, Additional Circuits in 1st floor
south wing and a fan coil unit,
2002 |
| 38 | | | Library, #01827, Protective Shields for FM Tanks,
2002 |
| 39 | | | Library, #01882, Carpet, Lights, Doors,
2002 |
| 40 | | | Library, #01968, Furniture for 1st floor,
2002 |
| 41 | | | Library, #02080, Stack lighting powerlink system,
2002 |
| 42 | | | Library, #02082, Install sliding glass doors room 101,
2002 |
| 43 | | | Library, #02100, Security System,
2002 |
| 44 | | | Library, #02123, Install Cylinder Locks,
2002 |
| 45 | | | Library, #02195, Install Track Lighting in video
conferencing room,
2002 |
| 46 | | | Library, #02250, Entrance Banners,
2002 |
| 47 | | | Library, #02263, Install 4 Branch circuit cables for
PDU,
2002 |
| 48 | | | Library, #02315, Replace Carpet Tiles in basement ATLC
room 40D,
2002 |
| 49 | | | Library, #02364, Furniture for Croslin Room,
2002 |
| 50 | | | Library, #02499, Paint and Carpet South Staff Hallway,
2002 |
| 51 | | | Library, #02799, Mount Security Web Cameras,
2002 |
| 52 | | | Lubbock Lake Landmark, #02344, Visitors Center Video
Security System,
2002 |
| 53 | | | Mass Communications, #00883, Renovate room 101,
2002 |
| 54 | | | Mass Communications, #01597, Repair Loose Carpet on
stairs,
2002 |
| 55 | | | Mass Communications, #01837, Campus Elevators-Phase
VII to bring E and G elevators into NEC Compliance,
2002 |
| 56 | | | Mass Communications, #02398, Construct a curved wall
for photo lab,
2002 |
| box | folder |
| 73 | 1 | | | Mass Communications, #02749, Renovate room 260 and
261,
2002 |
| 2 | | | Math, #01837, Campus Elevators-Phase VII to bring E
and G elevators into compliance with the NEC,
2002 |
| 3 | | | Math, #02128, Replace lamps and ballasts,
2002 |
| 4 | | | Math, #02577, Modular furniture workstations for
Vietnam Center,
2002 |
| 5 | | | McClellan Hall, #02305, Carpet Room 210 and 211,
2002 |
| 6 | | | Mechanical Engineering, #01837, Campus Elevators-Phase
VII to bring E and G elevators into NEC Compliance,
2002 |
| 7 | | | Mechanical Engineering, #02014, Carpet graphics lab
and 2 offices (224),
2002 |
| 8 | | | Mechanical Engineering, #02382, Vent System for room
120,
2002 |
| 9 | | | Mechanical Engineering, WO 103119, Repair existing
carpet room 222,
2002 |
| 10 | | | Men's Gym, #01907, Annual Carpet-Replace Carpet room
104,
2002 |
| 11 | | | Men's Gym, #02153, Roof Warranty Work,
2002 |
| 12 | | | Men's Gym, #02708, Replace Carpet,
2002 |
| 13 | | | Men's Gym, CR119718, Replace Roof, 1 of 2,
2002 |
| 14 | | | Men's Gym, CR119718, Replace Roof, 2 of 2, 25 prints,
2002 |
| 15 | | | Men's Gym, WO089737, Repair Carpet Room 207,
2002 |
| 16 | | | Men's/Women's Gym, #02254, Building Name Changes,
2002 |
| 17 | | | Museum, #01631, Replace Roof, 1 of 2,
2002 |
| 18 | | | Museum, #01631, Replace Roof, 2 of 2,
2002 |
| 19 | | | Museum, #01837, Campus Elevators-Phase VII to bring E
and G elevators into compliance with the NEC,
2002 |
| 20 | | | Museum, #02141, Upgrade Security System,
2002 |
| 21 | | | Music, #01839, Carpet and Window Treatments in room
201,
2002 |
| 22 | | | Music, #01907, Annual Carpet-Annual Carpet
Replacement,
2002 |
| 23 | | | Music, #02208, Replace Carpet in room 104 and 104A,
2002 |
| 24 | | | Music, W0102869, Repair Carpet entrance to room 11,
2002 |
| 25 | | | New Deal Farm, #01804, Replace entire X-Fan in
building 809,
2002 |
| 26 | | | New Deal Farm, #01806, Replace Entire X-Fan in
building 811,
2002 |
| 27 | | | Petroleum Engineering, #00272, Upgrade HVAC Controls,
2002 |
| 28 | | | Petroleum Engineering, #01748, Install Fume Hood,
2002 |
| 29 | | | Physical Plant, #00683, Renovate Room 12A,
2002 |
| 30 | | | Physical Plant, #00816, Furniture room 3C, 3JA, 3F,
2002 |
| 31 | | | Physical Plant, #01023, Renovate Central Warehouse,
2002 |
| 32 | | | Physical Plant, #01798, Furniture for room 4,
2002 |
| 33 | | | Physical Plant, #02098, RFQ for Asbestos Monitoring,
2002 |
| 34 | | | Physical Plant, #02221, Install Fiber runs to various
locations within PP,
2002 |
| 35 | | | Physical Plant, #02292, Furniture for room 8A,
2002 |
| 36 | | | Physical Plant, #02484, Renovate restroom in grounds
maintenance shop,
2002 |
| 37 | | | Plant Sciences, #00856, Renovate room 210, 211, 212, 1
of 2,
2002 |
| 38 | | | Plant Sciences, #00856, Renovate Room 210, 211, 212, 2
of 2,
2002 |
| 39 | | | Plant Sciences, #01866, Install Carpet in room 203 and
203A,
2002 |
| 40 | | | Plant Sciences, #01899, Install Five Alarm System,
2002 |
| 41 | | | Plant Sciences, #01988, Blinds in room 150B,
2002 |
| 42 | | | Psychology, #01079, Renovate Room B2, 2 prints,
2002 |
| 43 | | | Psychology, #01691, Design Space Planning for room
201B,
2002 |
| 44 | | | Psychology, #01837, Campus Elevators-Phase VII to
bring E and G elevators into compliance with NEC,
2002 |
| 45 | | | Rancing Heritage Center, #02140, Replace Transformers,
2002 |
| 46 | | | Recreation Center, #01807, New Outdoor Pursuits
Center,
2002 |
| 47 | | | Recreation Center, #02106, Furniture for room 206,
2002 |
| 48 | | | Recreation Center, #02449, ADA Renovations to Elevator
#1,
2002 |
| 49 | | | Recreation Center, #02493, Renovate 1st and 2nd floor
Restroom for ADA,
2002 |
| 50 | | | Reese Center, #01434 Upgrade office areas in building
551 and 555,
2002 |
| box | folder |
| 74 | 1 | | | Reese Center, #01782, Wind Engineering Research Site,
1 of 2,
2002 |
| 2 | | | Reese Center, #01782, Wind Engineering Research Site,
2 of 2,
2002 |
| 3 | | | Reese Center, #02355, HVAC Building 552; Modify High
Bays; ADA Restrooms,
2002 |
| 4 | | | Reese Center, #02393, Install Security Enhancement
Measures,
2002 |
| 5 | | | Reese Center, WO 110010, Frame existing marker board,
2002 |
| 6 | | | Sanitary Sewer Systems, #02541, Pipe discharge from
sump pump in Thompson Vault,
2002 |
| 7 | | | Science, #00101, Renovate room 118, 1 of 2,
2002 |
| 8 | | | Science, #00101, Renovate room 118, 2 of 2,
2002 |
| 9 | | | Science, #00331, Install Laser Interlock in lab #28,
2002 |
| 10 | | | Science, #00706, Renovate Room 326, 1 of 2,
2002 |
| 11 | | | Science, #00706, Renovate Room 326, 2 of 2,
2002 |
| 12 | | | Science, #00976, Remodel men's and women's restrooms
on 2nd floor,
2002 |
| 13 | | | Science, #01669, Replace Fume vent in room 208,
2002 |
| 14 | | | Science, #01837, Campus Elevators-Phase VII to bring E
and G elevators into compliance with the NEC,
2002 |
| 15 | | | Science, #01890, Install Laser Lights in room 104 and
shutter in room 31,
2002 |
| 16 | | | Science, #02373, Remodel Room 123,
2002 |
| 17 | | | Sewer Lift Station, #01911, Replace Emergency
Generator,
2002 |
| 18 | | | Sewer Lift Station, #01914, Replace Water Control
Panel,
2002 |
| 19 | | | Sneed-Snack Bar, #01969, Tracking of Inspector Time,
2002 |
| 20 | | | Southwest Collection/Special Collections Library,
#01837, Campus Elevators-Phase VII to bring E and G elevators into NEC
Compliance,
2002 |
| 21 | | | Stangel/Murdough, #01550, Recommend cooling coils for
stangel AHU #9, 10, 11, and Murdough #6 and 8,
2002 |
| 22 | | | Stangel/Murdough, #01732, Repair/Replace Roof as
needed,
2002 |
| 23 | | | Stangel/Murdough, #01734, Replace AHU and Plant
Controls,
2002 |
| 24 | | | Student Rec Center, #02202 Change Out formica
countertops,
2002 |
| 25 | | | Texas Tech Plaza, #02121, Carpet 301B,
2002 |
| 26 | | | Texas Tech Plaza, #02353, Skyview Seating,
2002 |
| 27 | | | Texas Tech Plaza, W0110725, Provide paint sheme
design,
2002 |
| 28 | | | Thompson Hall, #01140, Review Survey to enhance the
current area,
2002 |
| 29 | | | Tunnel Network, #02545, Repair Concrete slab at
Coleman Hall,
2002 |
| 30 | | | United Spirit Arena, #01557, Audio and Spotlight
Power,
2002 |
| 31 | | | United Spirit Arena, #02054, Remodel Office/Locker
Room, 1 of 2,
2002 |
| 32 | | | United Spirit Arena, #02054, Remodel Office/Locker
Room, 2 of 2,
2002 |
| 33 | | | United Spirit Arena, #02193, Expand Existing security
rooms and fire room,
2002 |
| 34 | | | United Spirit Arena, #02194, Locker Room Expansion,
2002 |
| 35 | | | United Spirit Arena, #02486, Evaluate Transformer
Feed,
2002 |
| 36 | | | University Center, #02102, Mini-Blinds Room 210,
2002 |
| 37 | | | University Center, #02404, New Signage for name change
to student union,
2002 |
| 38 | | | University Center, FP and C 98-70, Expansion and
Renvoation,
2002 |
| 39 | | | University Greenhouse, #01134, Addition and
Renovation, 1 of 2,
2002 |
| box | folder |
| 75 | 1 | | | University Greenhouse, #01134, Addition and
Renovation, 2 of 2,
2002 |
| 2 | | | University Plaza, #01471, Replace Roof,
2002 |
| 3 | | | University Plaza, #01483, KOHM Satellite Antenna
Relocation,
2002 |
| 4 | | | University Plaza, #01523, Renovate Skyviews
Restauraunt, 1 of 2,
2002 |
| 5 | | | University Plaza, #01523, Renovate Skyviews
Restauraunt, 2 of 2,
2002 |
| 6 | | | University Plaza, #01472-01, Renovate 6th Floor
Restroom,
2002 |
| 7 | | | University Plaza, #01472-02, Carpet and Tile for
Skyviews Restaurant,
2002 |
| 8 | | | University Police Department, #01902, Fire Alarm,
2002 |
| 9 | | | University Police Department, #02411, Install
Satellite,
2002 |
| 10 | | | West Hall, CR120726, Carpet room 244,
2002 |
| 11 | | | Women's Gym. #01388, Renovate Lab and Classroom,
2002 |
| 12 | | | Administration, Renovate rms 166, 171, #01772, 1 of 4,
2003 |
| 13 | | | Administration-Renovate rms 166, 171, #01772, 2 of 4,
2003 |
| 14 | | | Administration-Renovate rms 166, 171, #01772, 3 of 4,
2003 |
| 15 | | | Administration-Renovate rms 166, 171, #01772, 4 of 4,
2003 |
| 16 | | | Administration-Room 333 Blinds #1829,
2003 |
| 17 | | | Administration-Renovations for San Antonio Regional
Center #01905, 1 of 4,
2003 |
| 18 | | | Administration-Renovations for San Antonio Regional
Center #01905, 2 of 4, blueprints,
2003 |
| 19 | | | Administration-Renovations for San Antonio Regional
Center #01905, 3 of 4,
2003 |
| 20 | | | Administration-Renovations for San Antonio Regional
Center #01905, 4 of 4, blueprints,
2003 |
| box | folder |
| 76 | 1 | | | Administration-Office Furniture Room 171 #02135,
2003 |
| 2 | | | Administration-Replace North Roof Selection #01872,
2003 |
| 3 | | | Administration-Replace Carpet #02199,
2003 |
| 4 | | | Administration-Glass for Desktops-Room 171 #02677,
2003 |
| 5 | | | Administration-West Wing Carpet #02800,
2003 |
| 6 | | | Administration-Carpet and Paint 3rd Floor #02940,
2003 |
| 7 | | | Administration-Renovate room 337 into a conference
room #03204,
2003 |
| 8 | | | Administration-Carpet Room 301-309, 311-312, 314, 316,
318, 320 #03303,
2003 |
| 9 | | | Administration-Window Blinds Room 226 and 228 #03268,
2003 |
| 10 | | | Administration-Modify room 101 JA#02594,
2003 |
| 11 | | | Administration-Create a door way between 346 and 348
#03442,
2003 |
| 12 | | | Administration-Add Electrical outlets for multimedia
equipment #3304,
2003 |
| 13 | | | Ag Pavilion Replace HVAC System #02512, 1 of 2,
2003 |
| 14 | | | Ag Pavilion Replace HVAC System #02512, 2 of 2,
2003 |
| 15 | | | Ag Plant Science-Renovate Room 214 #02359,
2003 |
| 16 | | | Ag Plant Sciences-Repair Exterior Tile #01875,
2003 |
| 17 | | | Ag Plant Sciences-Renovate Room 113A #02521,
2003 |
| 18 | | | Ag Plant Sciences-repair carpet room 261, 265
#WO120317,
2003 |
| 19 | | | Ag Sciences-Renovate 3rd Floor Restroom #01845, 1 of
2,
2003 |
| 20 | | | Ag Sciences-Renovate 3rd Floor Restroom #01845, 2 of
2,
2003 |
| 21 | | | Ag Sciences, Renovate Room 205A #3444,
2003 |
| 22 | | | Ag Sciences-Renovate Room 125 #02706,
2003 |
| 23 | | | Ag Sciences-Renovate Room 317C #02688,
2003 |
| 24 | | | Ag Plant Sciences-Renovate Room 109 #02294,
2003 |
| 25 | | | Animal Science-New Deal Farm Connect Utilities #02618,
2003 |
| 26 | | | Animal Science-Install Power Vent System #03110,
2003 |
| 27 | | | Aquatic Center, Acid Storage Ventilation #03355,
2003 |
| 28 | | | Aquatic Center-Drain at Front Door #03367,
2002 |
| 29 | | | Architecture-Restretch Carpet 10th Floor Dean's Office
WO#122212,
2003 |
| 30 | | | Architecture-Renovate 8th and 9th floors, #01832, 1 of
2,
2003 |
| 31 | | | Architecture-Renovate 8th and 9th floors, #01832, 2 of
2,
2003 |
| 32 | | | Architecture-Install Security Doors on 5th Floor,
#02516,
2003 |
| 33 | | | Art-Replace Roof #01632,
2003 |
| 34 | | | ATLC Remote Labs-Security Cameras for Remote Labs
#02740,
2003 |
| 35 | | | Biology-Humidification in room 412 #03380,
2003 |
| box | folder |
| 77 | 1 | | | Biology-Replace Autoclave #00446,
2003 |
| 2 | | | Biology-Renovate Room 601 and 604 #01371, 1 of 2,
2003 |
| 3 | | | Biology-Renovate Room 601 and 604 #01371, 2 of 2,
2003 |
| 4 | | | Biology-Campus Elevators- Directional Arrow, #01837,
2003 |
| 5 | | | Biology-Install Safety Showers #02518,
2003 |
| 6 | | | Biology-Furniture for Room 111 #02731,
2003 |
| 7 | | | Biology Audio/Visual Equipment #03164,
2003 |
| 8 | | | Bookstore-Relocation to Campus #02963,
2003 |
| 9 | | | Business Administration-Repair Carpet Room 252C
WO122409,
2003 |
| 10 | | | Business Administration-Reroof Tower, #01636, 1 of 3,
2003 |
| 11 | | | Business Administration-Reroof Tower, #01636, 2 of 3,
2003 |
| 12 | | | Business Administration-Rerooof Tower, #01636, 3 of 3,
2003 |
| 13 | | | Business Administration-Carpet Room 369B #01658,
2003 |
| 14 | | | Business Administration-Furniture and Carpet-Room 150
#02113,
2003 |
| 15 | | | Business Administration-Carpet Replacement-Room 403,
405, 407, 415, 417 #02690,
2003 |
| 16 | | | Business Administration-Draperies Room 150 #03021,
2003 |
| 17 | | | Business Administration-Space Planning and
Furniture-Room 902, 903, 917 #03049,
2003 |
| 18 | | | Business Administration-Replace Carpet #03280,
2003 |
| 19 | | | Campus-Renovate Grounds Maintenance Area Rooms #02437,
2003 |
| 20 | | | Campus Emergency Power-Emergency Power-15th and Flint
traffic light controller #02211,
2003 |
| 21 | | | Campus Exterior Lighting-Lightpoles #00933,
2003 |
| 22 | | | Campus Exterior Lighting-Rec Field and Tennis Courts
#00934,
2003 |
| 23 | | | Campus Exterior Lighting-Greenhouse C-13 Parking Lot
#02462,
2003 |
| 24 | | | Campus Exterior Lighting-Measure nighttime
illumination levels on Flint Ave. #03050,
2003 |
| 25 | | | CHACP1-Back Pressure turbine generator #02763,
2003 |
| 26 | | | CHACP1-Renovate Breakroom #02818,
2003 |
| 27 | | | CHACP1-Supply Pressure Readings #03553,
2003 |
| 28 | | | Chemical Engineering-Renovate room 103 #01384,
2003 |
| 29 | | | Chemical Engineering-Create Faculty Office #02482,
2003 |
| 30 | | | Chemical Engineering-Lab Bench room 110 #02504,
2003 |
| 31 | | | Chemical Engineering-Renovate Room B3A Phase 2 #02606,
2003 |
| 32 | | | Chemical Engineering-Relocate air vent value; Move NH3
Shut off of Plenum #02887,
2003 |
| 33 | | | Chemical Engineering-Install Chill Water Lab 111
#02927,
2003 |
| 34 | | | Chemistry-Island Roof Patch #01633, 1 of 2,
2003 |
| 35 | | | Chemistry-Island Roof Patch #01633, 2 of 2,
2003 |
| box | folder |
| 78 | 1 | | | Chemistry-4th Floor Plant Lab #01738,
2003 |
| 2 | | | Chemistry-Fume Hoods room 332 #02003,
2003 |
| 3 | | | Chemistry-Install lift clamp in room 001 #03614,
2003 |
| 4 | | | Child Development-Renovate Head Start Center #02362, 1
of 2,
2003 |
| 5 | | | Child Development-Renovate Head Start Center #2362, 2
of 2,
2003 |
| 6 | | | Civil Engineering-Install Fume Hood and Ancilliary
Equipment #01850,
2003 |
| 7 | | | Civil Engineering-Exhaust Fan/Eye Wash #03068,
2003 |
| 8 | | | Doak Comm-Repair Carpet Morris Cole's Office
#WO117409,
2003 |
| 9 | | | Doak Communications-Replace Electrical Distribution
Panels #01708,
2003 |
| 10 | | | Doak Communication-HVAC #02757,
2003 |
| 11 | | | Drane Hall-Renovate Room 113, 115 #02092,
2003 |
| 12 | | | Drane Hall-Install Doors #02623,
2003 |
| 13 | | | Drane Hall-Remodel 163 Lobby #02645,
2003 |
| 14 | | | Drane Hall-Furniture and Carpet Room 315 #02786,
2003 |
| 15 | | | Drane Hall-Secured Storage Facility #02911,
2003 |
| 16 | | | Drane Hall-Renovate Room 166 #03017,
2003 |
| 17 | | | Education-Upgrade lighting room 200 #03170,
2003 |
| 18 | | | Electrical Engineering-Repair Carpet Room 217
#WO113805,
2003 |
| 19 | | | Engineering Center-Exterior Repairs #01873,
2003 |
| 20 | | | Engineering Center-Replace Elevator Jack #02383,
2003 |
| 21 | | | Engineering Center-Install Fan Coil Unit #03060,
2003 |
| 22 | | | English-English Fiber to Bell Tower #02985,
2003 |
| 23 | | | Exercise Sciences Center-Replace Energy Management
System #03011,
2003 |
| 24 | | | Food Tech-Install Smokehouse #02139,
2003 |
| 25 | | | Foreign Language-Renovate Room 200 #03262,
2003 |
| 26 | | | Foreign Language-Renovate Room 022 into a computer
classroom #03331,
2003 |
| 27 | | | Foreign Language-Renovations to the LAnguage Learning
Laboratory, #03261,
2003 |
| 28 | | | Foreign Language-Install Door in room 1A #03260,
2003 |
| 29 | | | Gates Hall-Repair/Replace Roof #01962, 1 of 2,
2003 |
| 30 | | | Gates Hall-Repair/Replace Roof #01962, 2 of 2,
2003 |
| 31 | | | Goddard Range and Wildlife-Interior Painting #01164,
2003 |
| 32 | | | Goddard Range and Wildlife-Install Fire Alarm System
#01900,
2003 |
| 33 | | | Goddard Range and Wildlife-Replace HVAC Controls
#02048,
2003 |
| 34 | | | Goddard Range and Wildlife-Lighting room 203, 207,
101; Reduce air handler noise room 203, #02622,
2003 |
| 35 | | | Goddard Range and Wildlife-Install Carpet room 107,
108, 01, #02179,
2003 |
| 36 | | | Holden Hall-Renovate Room 203E, #02515,
2003 |
| 37 | | | Holden Hall-Renovate Room 203 into 2 offices, #02764,
2003 |
| 38 | | | Holden Hall-Annual Carpet Replacement room 102 #03059,
2003 |
| box | folder |
| 79 | 1 | | | Holden Hall-Install Lights and Dimmer in room 2E
#03127,
2003 |
| 2 | | | Holden Hall-Annual Carpet-Replace Carpet rm 34, 35,
35A, 36, 37, #00832,
2003 |
| 3 | | | Holden Hall-Enlarge Room 02C #01942,
2003 |
| 4 | | | Holden Hall-Install Carpet room 119 #01400,
2003 |
| 5 | | | Holden Hall-Space Design #02143,
2003 |
| 6 | | | Holden Hall-Multi-Media room 104, 150, #02446,
2003 |
| 7 | | | Holden Hall-Construct Walls in room 79 #03483,
2003 |
| 8 | | | Housing Services-Water Softners #02638,
2003 |
| 9 | | | Human Sciences-Renovate Room 507, #02394, 1 of 2,
2003 |
| 10 | | | Human Sciences-Renovate Room 507 #02394, 2 of 2,
2003 |
| 11 | | | Human Sciences-Reconnect Thermostat room 306C #02808,
2003 |
| 12 | | | Human Sciences-Ventilate Vestibule by room 152 #02809,
2003 |
| 13 | | | Human Sciences-Construct vestibule by room 152 #02833,
2003 |
| 14 | | | Human Sciences-Construct Vestibule area room 403 and
403A, #02992,
2003 |
| 15 | | | Human Sciences-Renovate Suite 172 #03056,
2003 |
| 16 | | | Human Sciences-Renovate Room 222 #03396,
2003 |
| 17 | | | International Textile Center-Build Explosive research
site se of ITC on ELoop289, #02077,
2003 |
| 18 | | | International Textile Center-Install natural gas line
#02732,
2003 |
| 19 | | | Industrial Engineering-Install Power Circuits #02643,
2003 |
| 20 | | | Journalism-Renovate Room 210 #02108,
2003 |
| 21 | | | Junction Center-Carpet Robert Packard Lab with Carpet
Tile #01694,
2003 |
| 22 | | | Junction Center-Replace Carpet in bldgs 982, 990, 992,
984 #00783,
2003 |
| 23 | | | KTXT-Remove and Patch Intake air vent #03182,
2003 |
| 24 | | | Law-Remodel Career Services Center, Room 108N #01385,
2003 |
| 25 | | | Law-Repair Carpet in basement in front of elevator
WO#121727,
2003 |
| 26 | | | Law-Room 127 Work Stations #2033,
2003 |
| 27 | | | Law-Furniture for 1st Floor of Law Library #02018,
2003 |
| 28 | | | Law-Renovate room 126A #02400,
2003 |
| 29 | | | Law-Furniture for Staff Lounge #02484,
2003 |
| 30 | | | Law-New-Lighting 2nd/3rd Floors #02505,
2003 |
| 31 | | | Law, #02506, Create Office Administrative Lobby,
2003 |
| 32 | | | Law-Power Upgrade in Server room #02554,
2003 |
| 33 | | | Law-Carpet in front of carrels 229 and 230 #02556,
2003 |
| 34 | | | Law-Room 106 and 107 seating #02667,
2003 |
| 35 | | | Law-Reception Desk #02819,
2003 |
| 36 | | | Law-Install frame for sun screen on skylight room 108F
#02881,
2003 |
| 37 | | | Law-#02882, Furniture for Dean's Office,
2003 |
| 38 | | | Law, #02915, Room 106 and 107-Riser Modification for
ADA,
2003 |
| 39 | | | Law-#02987, Install fan coil-room 227,
2003 |
| 40 | | | Law-#03003, Replace Elevator #1 Jack,
2003 |
| 41 | | | Law, #03093, Cable Path and Power Receptacle for
Computers,
2003 |
| 42 | | | Law-#03239, Renovate room 121B,
2003 |
| 43 | | | Law-#03449, Upgrade multimedia equipment,
2003 |
| 44 | | | Library, #01204, Install Communication Room
Protection,
2003 |
| 45 | | | Library, #01752, Server room cooling-rooms 74, 76, 78,
1 of 2,
2003 |
| 46 | | | Library, #01752, Server room cooling-rooms 74, 76, 78,
2 of 2,
2003 |
| box | folder |
| 80 | 1 | | | Library, #02424, Install Door and Frame Room 5,
2003 |
| 2 | | | Library, #02495, ATLC: Renovate room 59, 61, 63, 65,
2003 |
| 3 | | | Library, #02601, ATLC Cubicle Furniture,
2003 |
| 4 | | | Library, #02633, Wireless Network-Library to ITC,
2003 |
| 5 | | | Library, #02727, Furniture-room 61,
2003 |
| 6 | | | Library, #02779, Divide room 145 of the TLTC into 2
offices,
2003 |
| 7 | | | Library, #02796, Stacks levels 1-5,
2003 |
| 8 | | | Library, #02806, Exterior lighting, Refurbish steps,
Plant grass,
2003 |
| 9 | | | Library, #02977, HVAC Room 105,
2003 |
| 10 | | | Library, #03053, Furniture ATLC West Basement,
2003 |
| 11 | | | Library, #03090, ATLC furnishings-reference area and
common area,
2003 |
| 12 | | | Lubbock Lake Landmark, #02173, Exterior Repairs,
2003 |
| 13 | | | Maedgen Theatre, #00972, Renovation, 1 of 3,
2003 |
| 14 | | | Maedgen Theatre, #00972, Renovation, 2 of 3,
2003 |
| 15 | | | Maedgen Theatre, #00972, Renovation, 3 of 3,
2003 |
| 16 | | | Maedgen Theatre, #02502, Replace Seating,
2003 |
| 17 | | | Maedgen Theatre, #02514, Install Smoke Detectors,
2003 |
| 18 | | | Maedgen Theatre, #02530, Emergency Generator,
2003 |
| 19 | | | Main Campus, #01429, Install monitoring and control
system,
2003 |
| 20 | | | Main Campus, #02979, Self-Help work in room 114 of
Posey Elementary,
2003 |
| 21 | | | Mass Communications, #02060, Lighting Study,
2003 |
| 22 | | | Mass Communications, #02188, Replace Auto Trans
Switch,
2003 |
| 23 | | | Math, #01638, Renovations,
2003 |
| 24 | | | McClellan Hall, #02380, Convert room 214A to Office,
2003 |
| 25 | | | Meat Lab, #02187, Replace Roof,
2003 |
| 26 | | | Meat Lab, #03205, Moisture Problem,
2003 |
| 27 | | | Murdough Hall, #02936, Repair Roof,
2003 |
| 28 | | | Murdough Hall, #03499, Re-Roof Murdough Hall,
2003 |
| 29 | | | Museum, #01041, Replace Lighting in Print Gallery,
2003 |
| 30 | | | Museum, #02596, Vatican Security,
2003 |
| 31 | | | Museum, #02661, Move Doorway,
2003 |
| 32 | | | Music, #02391, Replace Roof,
2003 |
| 33 | | | Music, #02666, Install Bigger cooling coil on A/H #1,
2003 |
| 34 | | | Music, #02865, Build ADA Accessible Ramp on 1st Floor,
2003 |
| 35 | | | Music, #03596, Replace floor covering room 252,
2003 |
| 36 | | | National Ranching Heritage, #03294, Upgrade the Brush
Arbor,
2003 |
| 37 | | | Petroleum Engineering, #01932, Replace Lighting,
2003 |
| 38 | | | Petroleum Engineering, #02836, Replace Carpet in room
112, 113, 114, 115,
2003 |
| 39 | | | Physical Plant, #02788, Chairs for John Burton's
Office,
2003 |
| 40 | | | PrintTech, #02654, Provide 6" exhaust duct for a new
printing press,
2003 |
| 41 | | | PrinTech, #02733, Retrofit visible light source on
Heidlburg press,
2003 |
| 42 | | | PrinTech, #03341, Barricade for new printing press
console,
2003 |
| 43 | | | Psychology, #00265, ADA Restroom 1st floor,
2003 |
| 44 | | | Psychology, #01991, Upgrade Lighting,
2003 |
| 45 | | | Psychology, #02407, Renovate room b14, 1 of 3,
2003 |
| 46 | | | Psychology, #2407, Renovate room b14, 2 of 3,
2003 |
| 47 | | | Psychology, #02407, Renovate room b14, 3 of 3,
2003 |
| box | folder |
| 81 | 1 | | | Psychology, #02454, Remodel room 109,
2003 |
| 2 | | | Recreation Center, #01973, Sport Lighting Evaluation,
2003 |
| 3 | | | Recreation Center, #03475, Renovate room 203,
2003 |
| 4 | | | Reese Center, #00624, Provide 200 Meter Guyed Tower
for Wind Engineering Research Center, 1 of 3, |
| 5 | | | Reese Center, #00624, Provide 200 Meter Guyed Tower
for Wind Engineering Research Center, 2 of 3, 14 prints,
2003 |
| 6 | | | Reese Center, #00624, Provide 200 Meter Guyed Tower
for Wind Engineering Research Center, 3 of 3,
2003 |
| 7 | | | Reese Center, #01948, Egress Lighting,
2003 |
| 8 | | | Reese Center, #02094, Upgrade Conference Room,
2003 |
| 9 | | | Reese Center, #02743, Network Connectivity between
building 555 and 250/350,
2003 |
| 10 | | | Reese Center, #02831, Building 555 room 106 Furniture
Items,
2003 |
| 11 | | | Reese Center, #02959, Remove existing seamp coolers
and cap off roof,
2003 |
| 12 | | | Reese Center, #02960, Front Restrooms, Name Switch,
2003 |
| 13 | | | Reese Center, #03224, Install Drop Ceiling in Building
250 room 108, 109,
2003 |
| 14 | | | Science #00981, Renovate room 7 for multi-media
classroom, 1 of 3,
2003 |
| 15 | | | Science #00981, Renovate room 7 for multi-media
classroom, 2 of 3,
2003 |
| 16 | | | Science #00981, Renovate Room 7 for multi-media
classroom, 3 of 3,
2003 |
| 17 | | | Science, #01062, Abate floor of room 7,
2003 |
| 18 | | | Science, #03199, Auxilary Cooling Room 29,
2003 |
| 19 | | | Student Union, #02507, Exterior Repairs,
2003 |
| 20 | | | Texas Tech House, #01977, Install Communication
Conduits,
2003 |
| 21 | | | Texas Tech House, #02951, Renovate Pool House,
2003 |
| 22 | | | Texas Tech House, #02952, Install new sunroom,
2003 |
| 23 | | | Texas Tech House, #02953, Design and Install New
Bathroom,
2003 |
| 24 | | | Texas Tech House, #02956, Close Off South door to
bathroom,
2003 |
| 25 | | | Texas Tech Plaza, #02461, Renovate 6th Floor Elevator
Lobby,
2003 |
| 26 | | | Texas Tech Plaza, #02532, Replace Evaporative Air
Conditioner,
2003 |
| 27 | | | Texas Tech Plaza, #02737, Install Wall Fabric on
elevator lobby walls 5th floor,
2003 |
| 28 | | | Texas Tech Plaza, #02816, Roof Anchors,
2003 |
| 29 | | | Texas Tech Plaza, #02931, Replace Basement AHU and
Condensing Unit,
2003 |
| 30 | | | Texas Tech Plaza, #02991, UPD Briefing room for
traffic and parking,
2003 |
| 31 | | | Tunnel Network, #02334, Repair Tunnel Structure,
2003 |
| 32 | | | Tunnel Network, #02974, Lighting and Security,
2003 |
| 33 | | | United Spirit Arena, #02374, Halogen Lights,
2003 |
| 34 | | | United Spirit Arena, #02450, Fire Wall,
2003 |
| 35 | | | United Spirit Arena, #02588, Simplex Card Reader,
2003 |
| 36 | | | United Spirit Arena, #02821, Show Power Transformers,
2003 |
| 37 | | | United Spirit Arena,, #03082, Repair Carpet in Hall of
Honor,
2003 |
| 38 | | | United Spirit Arena, #03376, Storage Facility,
2003 |
| 39 | | | United Spirit Arena, #03377, Provide Doors in Food
Court Area,
2003 |
| 40 | | | University Greenhouse, #02929, Enclose Sensitive
Equipment,
2003 |
| 41 | | | Warehouse 2305 Ave C, #03201, Storage Area for
University Press,
2003 |
| 42 | | | West Hall, #00350, Furniture for room 205,
2003 |
| box | folder |
| 82 | 1 | | | West Hall, #01834, Remodel room 205, 1 of 2,
2003 |
| 2 | | | West Hall, #01834, Remodel room 205, 2 of 2,
2003 |
| 3 | | | West Hall, #02306, Renovate Upward Bound Area-3rd
Floor,
2003 |
| 4 | | | West Hall, #02591, Blinds in room 214,
2003 |
| 5 | | | West Hall, #03150, Communications Closet HVAC,
2003 |
| 6 | | | West Hall, #03281, Replace Carpet,
2003 |
| 7 | | | West Hall, #03300, Renovate Room 335,
2003 |
| 8 | | | West Hall, #03301, 3rd Floor ADA Door Replacement,
2003 |
| 9 | | | West Hall, #03384, Renovate Room 335B,
2003 |
| 10 | | | West Hall, WO121728, Repair Carpet Room 118,
2003 |
| 11 | | | Women's Gym #01898, Install Fire Alarm System,
2003 |
| 12 | | | Administration, #02803, Elevator Repair,
2004 |
| 13 | | | Administration, #02803, Elevator Repair,
2004 |
| 14 | | | Administration, #02849, Reconfigure office areas,
2004 |
| 15 | | | Administration, #03033, Carpet 3rd Floors,
2004 |
| 16 | | | Administration, #03595, Room 212,
2004 |
| 17 | | | Administration, #03653, Renovate office for conference
room,
2004 |
| 18 | | | Administration, #03766, Overhead binder bins,
2004 |
| 19 | | | Administration, #03783, Carpet and Blinds,
2004 |
| 20 | | | Administration, #03880, Install Fire Alarm,
2004 |
| 21 | | | Administration Support, #03643, Sign for Texas Tech
Press,
2004 |
| 22 | | | Administration Support, #03900, Street Lighting,
2004 |
| 23 | | | Ag Ed Communications, #02871, Convert Room 100 into 2
offices,
2004 |
| 24 | | | Ag Ed. Communications, #03394, Renovate Room 00 and
100,
2004 |
| 25 | | | Ag Ed. Communications, #04033, Renovate elevator and
restrooms,
2004 |
| 26 | | | Ag Plant Sciences, #03858, Lighting for Building
facade-south side,
2004 |
| 27 | | | Agricultural Pavilion, #03931, Window Dressing,
2004 |
| 28 | | | Aquatic Center, #03266, Fiber Optic Lighting in pool,
2004 |
| 29 | | | Aquatic Center, #03355, AC Mechanical Room,
2004 |
| 30 | | | Architecture, #03168, Room 901 Cooling,
2004 |
| 31 | | | Art, #03824, Track Lighting,
2004 |
| 32 | | | Art, #04203, Room B09,
2004 |
| 33 | | | Athletics, #02834, Hammer Throw, 1 of 2,
2004 |
| 34 | | | Athletics, #02834, Hammer Throw, 2 of 2,
2004 |
| 35 | | | Biology, #03006, Replace Chiller unit,
2004 |
| 36 | | | Biology, #03164, Audio Visual, 1 of 2,
2004 |
| 37 | | | Biology, #03164, Audio Visual, 2 of 2,
2004 |
| box | folder |
| 83 | 1 | | | Business Administration, #02085, Renovate Room 169, 1
of 3,
2004 |
| 2 | | | Business Administration, #02085, Renovate Room 169, 2
of 3,
2004 |
| 3 | | | Business Administration, #02085, Renovate Room 169, 3
of 3,
2004 |
| 4 | | | Business Administration, #03375, Atennae on roof,
2004 |
| 5 | | | Business Administration, #03492, Carpet in Basement,
2004 |
| 6 | | | Business Administration, #03648, move door and create
3 rooms,
2004 |
| 7 | | | Business Administration, #03692, Carpet and Furnish
room 173,
2004 |
| 8 | | | Business Administration, #03693, Carpet and Furnish
room 272,
2004 |
| 9 | | | Business Administration, #03925, Room 61,
2004 |
| 10 | | | Campus, #01120, Exterior Lighting,
2004 |
| 11 | | | Campus, #02021, Bus Shelters,
2004 |
| 12 | | | Campus, #03346, Moveable classroom furniture,
2004 |
| 13 | | | Campus Tunnels, #02427, Communications problems,
2004 |
| 14 | | | CHACP1, #02840, Emergency Maintenance office,
2004 |
| 15 | | | CHACP1, #02958, wiring prints for elevator,
2004 |
| 16 | | | CHACP1, #03109, Remodel control room,
2004 |
| 17 | | | CHACP1, #03109, Repair wall of pipe deck,
2004 |
| 18 | | | CHACP1, #03342, Concrete Falling off walls,
2004 |
| 19 | | | CHACP1, #03342, Install automated controls,
2004 |
| 20 | | | CHACP1, #03644, Turbine generator,
2004 |
| 21 | | | CHACP1, #04184, Power circuit to transformer,
2004 |
| 22 | | | Charter Plains Hospital, #04068, Renovation,
2004 |
| 23 | | | Chemical Engineering, #01383, Renovate B3A, 1 of 4,
2004 |
| 24 | | | Chemical Engineering, #01383, Renovate B3A, 2 of 4,
2004 |
| 25 | | | Chemical Engineering, #01383, Renovate B3A, 3 of 4,
2004 |
| 26 | | | Chemical Engineering, #01383, Renovate B3A, 4 of 4,
2004 |
| 27 | | | Chemical Engineering, #03967, Ammonia Tank,
2004 |
| 28 | | | Chemical Engineering, #04011, Compressed air to
temporary lab,
2004 |
| 29 | | | Chemistry, #02384, upgrade elevator #2,
2004 |
| 30 | | | Chemistry, #02817, Install Electrical Service,
2004 |
| 31 | | | Chemistry, #03254, Replace Classroom Seating,
2004 |
| 32 | | | Chemistry, #03451 Move Fire Alarm Panel,
2004 |
| 33 | | | Chemistry, #03606, Seating-Room,
2004 |
| 34 | | | Chemistry, #03836, Relocate door-Room 118,
2004 |
| 35 | | | Chemistry, #03979, Rehab, Fume Hood,
2004 |
| 36 | | | Chitwood-Weymouth, #03671, Trash Chute,
2004 |
| 37 | | | Civil Engineering, #02385, Elevator Upgrade, 1 of 2,
2004 |
| 38 | | | Civil Engineering, #02385, Elevator Upgrade, 2 of 2,
2004 |
| box | folder |
| 84 | 1 | | | Computer Center, #03026, Diesel Generator,
2004 |
| 2 | | | Dan Law Field, #03255, Scoreboard Replacement,
2004 |
| 3 | | | Doak-Communications, #03374, Rooftop Packaged Unit,
2004 |
| 4 | | | Drane Hall, #03361, Computer Work Station,
2004 |
| 5 | | | Drane Hall, #03895, Carpet-Room 253,
2004 |
| 6 | | | East Engineering Research Center, #03866, Carpet Room
137,
2004 |
| 7 | | | East Engineering Research Center, #03962, Install
Doors,
2004 |
| 8 | | | Education, #04092, Room 106A,
2004 |
| 9 | | | Electrical Engineering, #03782, Upgrade Restrooms,
2004 |
| 10 | | | Engineering Center, #01713, Renovation of Engineering
Center,
2004 |
| 11 | | | Engineering Center #01713, Renovation of Engineering
Center, 1 of 2,
2004 |
| 12 | | | Engineering Center #01713, Renovation of Engineering
Center, 2 of 2,
2004 |
| 13 | | | Engineering Center, #03363, Renovation of 2nd and 3rd
floor,
2004 |
| 14 | | | Engineering Center, #03383, Asbestos Abatement for
Renovation, 1 of 2,
2004 |
| 15 | | | Engineering Center, #03383, Asbestos Abatement for
Renovation, 2 of 2,
2004 |
| 16 | | | Engineering Center, #03383, Asbestos Abatement for
Renovation, 1 of 2,
2004 |
| 17 | | | Engineering Center, #03383, Asbestos Abatement for
Renovation, 2 of 2,
2004 |
| 18 | | | Engineering Center, #03697, Repair Columns, 1 CD,
2004 |
| 19 | | | English, #02802, Temporary Repairs to Elevator,
2004 |
| 20 | | | English-Philosophy, #03515, Install Cooler for Server
Room,
2004 |
| 21 | | | Extended Studies, #03897, Scan and Update Building
Drawings,
2004 |
| 22 | | | Foreign Language, #03010, Replace Elevator Jack,
2004 |
| box | folder |
| 85 | 1 | | | Foreign Language, #03263, Remove Wall,
2004 |
| 2 | | | Fuller Track, #03889, Replace Pole Vault Box,
2004 |
| 3 | | | Fuller Track, #03996, Construct Platform,
2004 |
| 4 | | | Gordon/Bledsoe, #03709, Replace air washer in kitchen,
2004 |
| 5 | | | Hammer Throw, #02834, Relocation,
2004 |
| 6 | | | Hazardous Chemical Storage, #03009, Replace Roof,
2004 |
| 7 | | | Holden Hall, #02968, Replace classroom seating room
104,
2004 |
| 8 | | | Holden Hall, #03424, Renovate Room 221,
2004 |
| 9 | | | Holden Hall, #03578, Reception area for graduate
school,
2004 |
| 10 | | | Holden Hall, #03620, Build a wall with a door between
hall and room 03H,
2004 |
| 11 | | | Holden Hall, #03621, Enclose Room 03H,
2004 |
| 12 | | | Holden Hall, #03837, Reconfigure Room 102 to add
office space,
2004 |
| 13 | | | Horn/Knapp Dining, #03955, Repair ceiling in manager's
office,
2004 |
| 14 | | | Housing Services, #03077, 4 elevators modified to
comply with ADA standards,
2004 |
| 15 | | | Human Sciences, #02513, Renovate Elevator #1 to comply
with ADA standards,
2004 |
| 16 | | | Human Sciences, #02832, Multi-Media Improvements-Room
169,
2004 |
| 17 | | | Human Sciences, #03213, Make 2 rooms into 3
administration offices,
2004 |
| 18 | | | Human Sciences, #03292, Install Cubicle Furniture-room
302,
2004 |
| 19 | | | Human Sciences, #03466, Renovation of space into 6
offices,
2004 |
| 20 | | | Human Sciences, #03467, Extension of a half wall into
a full wall,
2004 |
| 21 | | | Human Sciences, #03468, Renovate Room 234,
2004 |
| 22 | | | Human Sciences, #03507, Provide ADA Restrooms,
2004 |
| 23 | | | Human Sciences, #03845, Add ice machine-room 119,
2004 |
| 24 | | | Human Sciences, #03966, Renovate Room 159,
2004 |
| 25 | | | Human Sciences, #03998, Replace Ceiling tiles and
lighting in Canyon Room,
2004 |
| 26 | | | Human Sciences, #03999, Redo Lighting in the
Breezeway,
2004 |
| 27 | | | I.T.C Wool Processing, #02387, AHU Replacement, 1 of
2,
2004 |
| 28 | | | I.T.C. Wool Processing, #02387, AHU Replacement, 2 of
2,
2004 |
| 29 | | | Industrial Engineering, #03417, Loading Dock,
2004 |
| 30 | | | J.J. Gibson Park, #03537, Landscape Lighting,
2004 |
| 31 | | | Jones SBC Stadium, #04041, Remodel of gate 4 and
design of gate 5,
2004 |
| 32 | | | Journalism, #03434, Student Media,
2004 |
| 33 | | | Jounalism, #03590, Make Room 203B ADA Accessible,
2004 |
| 34 | | | Journalism, #03591, Provide blackout window shade,
2004 |
| 35 | | | KOHM/KTXT, #02099, Transmitter Building,
2004 |
| 36 | | | KOHM/KTXT, #03249, Backup Power,
2004 |
| 37 | | | KTXT, #03681, Repair Water line,
2004 |
| 38 | | | L and H McLellan Memorial, #04064, Expand Room 205,
2004 |
| 39 | | | Law, #01825, Northwest Entrance Addition for Law
School clinic,
2004 |
| 40 | | | Law, #02019, Security Systems,
2004 |
| 41 | | | Law, #02341, Remove ACM from Projector in room 102,
2004 |
| 42 | | | Law, #02399, Loading Dock Renovation,
2004 |
| 43 | | | Law, #02399, Loading Dock renovation,
2004 |
| 44 | | | Law, #03206, Electrical Access to student desks in 8
classrooms,
2004 |
| box | folder |
| 86 | 1 | | | Law, #03368, Computer Workstations,
2004 |
| 2 | | | Law, #03437, Intercom System,
2004 |
| 3 | | | Law, #03446, Electrical Power Outlets,
2004 |
| 4 | | | Law, #03490, Convert a crawl space area,
2004 |
| 5 | | | Law, #03505, Window Screen for office 108F,
2004 |
| 6 | | | Law, #03506, Update Multimedia System,
2004 |
| 7 | | | Law, #03539, Renovate Registar's Office,
2004 |
| 8 | | | Law, #03673, Convert copy rooms into offices,
2004 |
| 9 | | | Law, #03724, Improve lighting in room 125,
2004 |
| 10 | | | Law, #03758, Replace panels in room 127 workstation,
2004 |
| 11 | | | Law, #03956, Enclose area next to room 128A,
2004 |
| 12 | | | Law, #03969, Install air vents in room 125,
2004 |
| 13 | | | Law, #04016, Renovate Room 122, 122A, 122h,
2004 |
| 14 | | | Law, #04020, Renovate room 120,
2004 |
| 15 | | | Law, #04021, Renovate room 121,
2004 |
| 16 | | | Law, #04046, Mini-blinds in room 126A,
2004 |
| 17 | | | Law, #04213, Install Bookcases in room 301D and 301E,
2004 |
| 18 | | | Law, #02390, Replace Columns, Cwas #00967,
2004 |
| 19 | | | Library, #03218, Garage Style Door,
2004 |
| 20 | | | Library, #03561, Fabric display panels,
2004 |
| 21 | | | Lubbock Lake Landmark, #03563, Install Fume Hood,
2004 |
| 22 | | | Maedgen Theatre, #00972, Renovate east Entrance and
seating area, 1 of 2,
2004 |
| 23 | | | Maedgen Theatre, #00972, Renovate east entrance and
seating area, 2 of 2,
2004 |
| 24 | | | Mass Communications, #02386, Upgrade Elevator #1,
2004 |
| 25 | | | Mass Communications, #02709, Replace Chilled Water
System,
2004 |
| 26 | | | McClellan Hall, #03493, Renovate 1st Floor Restroom, 1
of 2,
2004 |
| 27 | | | McClellan Hall, #03493, Renovate 1st Floor Restroom, 2
of 2,
2004 |
| 28 | | | Livestock Arena/Meats Lab, #02187, Rooftop Package
Unit,
2004 |
| 29 | | | Livestock Arena/Meats Lab, #03798, Lighting for C-10
Parking Lot,
2004 |
| 30 | | | Mechanical Engineering, #05-03924, Fill Tow Tank,
2004 |
| 31 | | | Mechanical Engineering, #04058, Install ventilation in
room 120,
2004 |
| 32 | | | Music, #01036, Hemmle Hall, 1 of 2,
2004 |
| 33 | | | Music, #01036, Hemmle Hall, 2 of 2,
2004 |
| 34 | | | Music, #03601, Replace Floor covering in main hallway,
2004 |
| 35 | | | Petroleum Engineering, #02875, Renovate Room 203,
2004 |
| 36 | | | Petroleum Engineering, #02912, Renovate Reception area
into offices,
2004 |
| 37 | | | Petroleum Engineering, #03100 Electrical Power for TTU
Test Wells Facility, 1 of 2,
2004 |
| 38 | | | Petroleum Engineering, #03100, Electrical Power for
TTU Test Wells Facility, 2 of 2,
2004 |
| 39 | | | Petroleum Engineering, #03161, Construct a lab room in
livermore,
2004 |
| 40 | | | Petroleum Engineering, #03801, Replace carpet in room
211, 212, 213,
2004 |
| 41 | | | Petroleum Engineering, #04080, Install Damper in room
105,
2004 |
| 42 | | | Physical Plant, #03813, Construction of 5000 sq. ft.
warehouse,
2004 |
| 43 | | | PrinTech, #01800, Install concrete slab; add
electrical power in power in pressroom, 1 of 2,
2004 |
| 44 | | | PrinTech, #01800, Install Concrete slab; add
electrical power in pressroom, 2 of 2,
2004 |
| box | folder |
| 87 | 1 | | | PrinTech, #03340, Shelf for press,
2004 |
| 2 | | | Ranching Heritage, #03997, Construct Milk and Meat
Cooler,
2004 |
| 3 | | | Rawls Golf Course, #03202, Run Conduit,
2004 |
| 4 | | | Recreation Center, #03455, Redesign waiting area in
main office,
2004 |
| 5 | | | Reese Center, #02599, Upgrade electrical 552,
2004 |
| 6 | | | Science, #03481, Room 326,
2004 |
| 7 | | | Southwest Collection/Special Collections Library,
#03422, Replace lighting with flourescent lighting,
2004 |
| 8 | | | Stangel Hall, #03498, Repair or replace roof,
2004 |
| 9 | | | Student Rec Center, #03175, Repair Roof Leaks,
2004 |
| 10 | | | Texas Tech Plaza, #02418, Remodel 2nd Floor,
2004 |
| 11 | | | Texas Tech Plaza, #029893, Upgrade, 5th Floor
Restrooms,
2004 |
| 12 | | | United Spirit Arena, #03771, Convert old Double T
shoppe into office space,
2004 |
| 13 | | | United Spirit Arena, #03793, Construct additional
office space inside Double T shoppe,
2004 |
| 14 | | | University Greenhouse, #03008, Replace Greenhouse
heaters, 15 prints,
2004 |
| 15 | | | UPD, University Police Department, #02781,
Modifications,
2004 |
| 16 | | | USDA Facility, #02625, Communication Conduit,
2004 |
| 17 | | | Wall Hall, #03504, Repair or Replace Roof,
2004 |
| 18 | | | West Hall, #03195, Renovate 1st Floor West Wing,
2004 |
| 19 | | | West Hall, #03403, Update Office-Room 216,
2004 |
| 20 | | | West Hall, #03554, Furniture-Room 335,
2004 |
| 21 | | | West Hall, #03558, Student Mediation Center,
2004 |
| 22 | | | West Hall, #03560, Renovate Room 335,
2004 |
| 23 | | | West Hall, #03812, Put Up Partition, room 335,
2004 |
| 24 | | | Wiggins Dining, #01939, Feasibility Study,
2004 |
| 24 | | | Wiggins Dining, #02637, Repair/Replace Roof,
2004 |
| 25 | | | Wiggins Dining, #03316, Replace SW Roof Area,
2004 |
| 26 | | | Wind Engineering, #03963, Review Electrical
Infrastructure of Reese Fieldsite (Runaway Tower I),
2004 |
| 27 | | | 10th Street 04364 Engineering Support earthwork,
lighting, and other utilities,
2005 |
| 28 | | | Abilene Campus 04901, Energy Audit,
2005 |
| 29 | | | Admin Support Center 03095 Create Cable Path,
2005 |
| 30 | | | Admin Upward Bound 03464 Room 313, 314, 316, 320, 1 of
3,
2005 |
| box | folder |
| 88 | 1 | | | Admin Upward Bound 03464, Room 313, 314, 316, 320, 2
of 3,
2005 |
| 2 | | | Admin Upward Bound 03464 Room 313, 314, 316, 320, 3 of
3,
2005 |
| 3 | | | Administration 04015 Order Furniture,
2005 |
| 4 | | | Administration 04344, Chancellor's Corridor,
2005 |
| 5 | | | Administration 04360 Room 208A,
2005 |
| 6 | | | Administration 04406 Room 171B,
2005 |
| 7 | | | Administration 04480 Repair Chairs,
2005 |
| 8 | | | Administration 04554 Room 246 Renovation,
2005 |
| 9 | | | Administration 04648, Room 353,
2005 |
| 10 | | | Administration 04649, Moveable table and arm seating,
2005 |
| 11 | | | Administration 04660 Cabinet for Room 164,
2005 |
| 12 | | | Administration 04701 Room 235 Renovation,
2005 |
| 13 | | | Ag Plant Science 03941 Replace Carpet,
2005 |
| 14 | | | Ag Plant Science 03995 Room 209 Repair,
2005 |
| 15 | | | Ag Plant Science 04029 Room 201,
2005 |
| 16 | | | Ag Plant Science 04048 Systems Furniture,
2005 |
| 17 | | | Ag Plant Science 04171 Landscape Architecture Letters
on Buildings,
2005 |
| 18 | | | Ag Plant Science 04212 Carpet for Room 214B,
2005 |
| 19 | | | Ag Sciences 04539 Restroom,
2005 |
| 20 | | | Ag Sciences 04780 Add Drain in Lab,
2005 |
| 21 | | | Ag Sciences 04796 Room 111,
2005 |
| 22 | | | Ag Sciences 04802 Annual Carpet,
2005 |
| 23 | | | Agriculture Pavillion 04994 Abate and Repair Ceiling,
2005 |
| 24 | | | Animal Science 04823 Replace Roof,
2005 |
| 25 | | | Architecture 03169 Acoustical Control in Studio Area,
1 of 2,
2005 |
| 26 | | | Architecture 03169 Acoustical Control in Studio Area,
2 of 2,
2005 |
| 27 | | | Architecture 04878 Door Security,
2005 |
| 28 | | | Architecture Library 04452 Lighting Improvements,
2005 |
| 29 | | | Art 03983 Replace Carpet Room B01, B02, B09A,
2005 |
| 30 | | | Art 04509 Renovate Kiln Area (Self Help),
2005 |
| 31 | | | Art 04656 Room 103 West Side,
2005 |
| 32 | | | Art and Sciences 04466 Sport Studies-Install
Wheelchair lift,
2005 |
| 33 | | | Athletic Services 02891 Sport Lighting System, 1 of 2,
2005 |
| box | folder |
| 89 | 1 | | | Athletic Services 02891 Sports Lighting System, 2 of
2,
2005 |
| 2 | | | Athletic Services 04750 New Soccer Fields and Track,
2005 |
| 3 | | | Athletic Services 04794 Install Lighting for
Bullpen-Garst Pavillion Women's Softball,
2005 |
| 4 | | | Biological Sciences 03286 New LCD Projector and
Screen,
2005 |
| 5 | | | Biology 03004 Repair Leaking Window System, 1 of 2,
2005 |
| 6 | | | Biology 03004 Repair Leaking Window System, 2 of 2,
2005 |
| 7 | | | Biology 04109 Room LH-100,
2005 |
| 8 | | | Biology 04568 Interactive Teaching System,
2005 |
| 9 | | | Biology 04909 Carbon Sheets on the Roof,
2005 |
| 10 | | | Biology Greenhouse 03019 Replace Cooling Pads,
2005 |
| 11 | | | Bledsoe Hall 03670 Elevator Repair,
2005 |
| 12 | | | Biology 03006 Low Temp Chiller,
2005 |
| 13 | | | Business Admin 03647 Create 2 Rooms and Closet,
2005 |
| 14 | | | Business Admin 03682 Renovate Room 151,
2005 |
| 15 | | | Business Admin 03843 Room 75 Renovation, 1 of 2,
2005 |
| 16 | | | Business Admin 03843 Room 75 Renovation, 2 of 2,
2005 |
| 17 | | | Campus Utilities 04153 Replace 8 pole lighting
needs-campus West of Library,
2005 |
| 18 | | | CHACP2 04427 Sewer Line Leaks,
2005 |
| 19 | | | Chancellor's Office 04253 Remove Wall Covering,
Texture and Paint Walls,
2005 |
| 20 | | | Chemical Engineering 03293 Install Fume Hood in Lab, 1
of 2,
2005 |
| 21 | | | Chemical Engineering 03293 Install Fume Hood in Lab, 2
of 2,
2005 |
| 22 | | | Chemical Engineering 03343 Provide Metal Laboratory
Building, 1 of 2,
2005 |
| 23 | | | Chemical Engineering 03343 Provide Metal Laboratory
Building, 2 of 2,
2005 |
| 24 | | | Chemical Engineering 04005 Fume Hood,
2005 |
| 25 | | | Chemistry 03099 Additional office space,
2005 |
| box | folder |
| 90 | 1 | | | Chemistry 04214 Enclose Sitting area-2nd Fl, S.Wing-W,
2005 |
| 2 | | | Chemistry 04215 Enclose sitting area-2nd floor S.
Wing-E,
2005 |
| 3 | | | Chemistry 04698, Replace Carpet Room 417,
2005 |
| 4 | | | Chemistry 04702 Carpet,
2005 |
| 5 | | | Chemistry 04703 Carpet,
2005 |
| 6 | | | Chemistry 04753 Room Divider-Room 234A,
2005 |
| 7 | | | Chitwood-Weymouth 03671 Install Trash Chute-Sam's
Place 2,
2005 |
| 8 | | | Civil Engineering 02712 Replace Roof, 1 of 3,
2005 |
| 9 | | | Civil Engineering 02712 Replace Roof, 2 of 3,
2005 |
| 10 | | | Civil Engineering 02712 Replace Roof, 3 of 3,
2005 |
| 11 | | | Civil Engineering 03069 Pipe RO and Chilled Water to
Room 226,
2005 |
| 12 | | | Civil Engineering 03769 Install Smoke Detectors in
Elevator Lobby,
2005 |
| 13 | | | Civil Engineering 03805 Replace Cabinets,
2005 |
| 14 | | | Communication SVCS 04133 Install Duct Cooling into
rooms (also see Human Sciences 04133),
2005 |
| 15 | | | Computer Center 04783 Power Distribution Add-On
Sidecar,
2005 |
| 16 | | | Computer Center 04882 Blade Enclosure,
2005 |
| 17 | | | Dan Law Field 04792 Sky Boxes,
2005 |
| 18 | | | Dan Law Field 04793 Upgrade Field Lighting,
2005 |
| 19 | | | Development Office 04232 Rooms 127 and 128,
2005 |
| 20 | | | Drane Hall 03775 Convert Room 165 to office space,
2005 |
| 21 | | | East Engineering Research Center 02626 Renovation, 1
of 9,
2005 |
| 22 | | | East Engineering Research Center 02626 Renovation, 2
of 9,
2005 |
| 23 | | | East Engineering Research Center 02626 Renovation, 3
of 9,
2005 |
| 24 | | | East Engineering Research Center 02626 Renovation, 4
of 9,
2005 |
| 25 | | | East Engineering Research Center 02626 Renovation, 5
of 9,
2005 |
| 26 | | | East Engineering Research Center 02626 Renovation, 6
of 9,
2005 |
| 27 | | | East Engineering Research Center 02626 Renovation, 7
of 9,
2005 |
| box | folder |
| 91 | 1 | | | East Engineering Research Center 02626 Renovation, 8
of 9,
2005 |
| 2 | | | East Engineering Research Center 02626 Renovation, 9
of 9,
2005 |
| 3 | | | East Engineering Research Center 04428 Lower Lighting
at ITC,
2005 |
| 4 | | | East Research Center 03802 Replace Carpet-ITC,
2005 |
| 5 | | | Education 04129 Room 106 A,
2005 |
| 6 | | | Engineering Center 04180 Renovate Room Look, 1 of 3,
2005 |
| 7 | | | Engineering Center 04180 Renovate Room Look, 2 of 3,
2005 |
| 8 | | | Engineering Center 04180 Renovate Room look, 3 of 3,
2005 |
| 9 | | | Engineering Center 04570 Room 100,
2005 |
| 10 | | | Engineering Center 04729 signs,
2005 |
| 11 | | | English Philosophy 04572 Room 356 B,
2005 |
| 12 | | | Exercise Sciences 03549 Guardrail,
2005 |
| 13 | | | Exercise Sciences 04304 Room 103-Gym,
2005 |
| 14 | | | Exercise Sciences 04337 Room 118 A,
2005 |
| 15 | | | FP and C 04645 Annual Carpet,
2005 |
| 16 | | | Golf Course 04582 Propane Heaters for Hitting Bays,
2005 |
| 17 | | | Holden Hall 04801 Annual Carpet,
2005 |
| 18 | | | Holden Hall 04889 Carpet Room 110,
2005 |
| 19 | | | Horn/Knapp 03362 Parking Lot Lighting,
2005 |
| 20 | | | Human Sciences 03426 Renovate Room 269, 1 of 2,
2005 |
| 21 | | | Human Sciences 03426 Renovate Room 269, 2 of 2,
2005 |
| 22 | | | Human Sciences 03869, Abate Room, 605,
2005 |
| 23 | | | Human Sciences 03479 Replace Fire Alarm System, 1 of
2,
2005 |
| 24 | | | Human Sciences 03479 Replace Fire Alarm System, 2 of
2,
2005 |
| 25 | | | Human Sciences 04133 Cooling in Telephone Equipment
Rooms (Also see Comm Svcs 04133),
2005 |
| 26 | | | Human Sciences o4622 Display Cases,
2005 |
| 27 | | | Human Sciences 04643 Replace Carpet-Room 601,
2005 |
| 28 | | | Human Sciences 04352 Renovate Room 306A,
2005 |
| 29 | | | Industrial Engineering 04031 Install Wall and Lights,
2005 |
| 30 | | | Industrial Engineering 04621 RO Water-Room 112,
2005 |
| 31 | | | International Cultural Center Library 04531 Signage
for ICC,
2005 |
| 32 | | | International Cultural Center Library 04585 Add
Surveillance Camera,
2005 |
| box | folder |
| 92 | 1 | | | Jones SBC Stadium 03850 Remove Wall Between Room 205
and 206,
2005 |
| 2 | | | Jones SBC Stadium 04384 New Doors at Press Level,
2005 |
| 3 | | | Jones SBC Stadium Athletics Office 04240 Build
Wardrobe Cabinet,
2005 |
| 4 | | | Jounalism 03592 Provide Better Lighting,
2005 |
| 5 | | | KTXT TV 03275 Building Expansion-Transmitter Addition,
1 of 2,
2005 |
| 6 | | | KTXT TV 03275 Building Expansion-Transmitter Addtion,
2 of 2,
2005 |
| 7 | | | KTXT TV 04662 Room 112,
2005 |
| 8 | | | Law 03447 Security System Upgrade,
2005 |
| 9 | | | Law 03679 Install Security Crashbars,
2005 |
| 10 | | | Law 04128 Lounge Furniture and Tables,
2005 |
| 11 | | | Law 04167 Systems Renovation,
2005 |
| 12 | | | Law 04169 Renovate Room 5B and 5C,
2005 |
| 13 | | | Law 04181 Add two Cameras,
2005 |
| 14 | | | Law 04418 Room 223 Window,
2005 |
| 15 | | | Law 04463 Renovate Room 226a,
2005 |
| 16 | | | Law 04494 Close off Hallway to room 126,
2005 |
| 17 | | | Law 04628 Library Tables,
2005 |
| 18 | | | Law 04767 Access Control-2nd and 3rd Floors,
2005 |
| 19 | | | Law 04836 Room 109 Custom Storage,
2005 |
| 20 | | | Law 04858 Add Single Workstation,
2005 |
| 21 | | | Library 03089 Furnishings for Student Computing Area,
1 of 2,
2005 |
| 22 | | | Library 03089 Furnishings for Student Computing Area,
2 of 2,
2005 |
| 23 | | | Library 03803 Add 3 Offices to TLTC Room 155,
2005 |
| 24 | | | Library 04179 Library Tornado Alert,
2005 |
| 25 | | | Library 04410 Renovate Room 012,
2005 |
| 26 | | | Library 04505 Lighting Controls,
2005 |
| 27 | | | Library 04536 Install Window Between Room 23 and 25,
2005 |
| 28 | | | Library 04625 CAD Fire Suppression System,
2005 |
| 29 | | | Library 04712 Lighting Control,
2005 |
| 30 | | | Library 05-04745 Room 074,
2005 |
| 31 | | | Library 05-04759 Add Paging Microphone to Fire Alarm
Panel,
2005 |
| 32 | | | Library 05-04778 Guards for Paper Cutter,
2005 |
| 33 | | | Library 05-04806 Cut Countertop to Permit a Thru-way,
2005 |
| 34 | | | Library 05-04814 Additional HVAC,
2005 |
| 35 | | | Library 05-04917 DVD/CD Cabinets,
2005 |
| 36 | | | McClellan Hall 04035 Foyer,
2005 |
| 37 | | | McClellan Hall 04137 Upgrade Existing Space in Room
210 and 211,
2005 |
| 38 | | | Meat Lab 05-03454 Construct Poultry Processing Area,
2005 |
| 39 | | | Meat Lab 05-04479 Control of Condensation,
2005 |
| 40 | | | Meat Lab 05-04613 Install Light,
2005 |
| 41 | | | Mechanical Engineering 03054 Replace Elevator #2 Jack,
1 of 2,
2005 |
| 42 | | | Mechanical Engineering #03054 Replace Elevator #2
Jack, 2 of 2,
2005 |
| box | folder |
| 93 | 1 | | | Mechanical Engineering 04083 Add a Doorway-Rooom 224,
2005 |
| 2 | | | Mechanical Engineering 04348, Widen Door to Room 124,
2005 |
| 3 | | | Mechanical Engineering 04356, Check Floor Loading,
2005 |
| 4 | | | Mechanical Engineering 04657, Add Electrical Lines,
2005 |
| 5 | | | Mechanical Engineering, 04862 Carpet Room 149,
2005 |
| 6 | | | Mechanical Engineering 04944, Install Filters on
Water Fountains,
2005 |
| 7 | | | Mechanical Engineering 04952, Epoxy Top Benches,
2005 |
| 8 | | | Museum 03271, Renovate NW Suite Area, 1 of 2,
2005 |
| 9 | | | Museum 03271, Renovate NW Suite Area, 2 of 2,
2005 |
| 10 | | | Museum 03711, Replace Roof Areas,
2005 |
| 11 | | | Museum 03848, Install Security Cameras,
2005 |
| 12 | | | Museum 04095, Exterior Work,
2005 |
| 13 | | | Museum 04423, Unit A Balcony,
2005 |
| 14 | | | Museum 04556, Install Light Fixtures,
2005 |
| 15 | | | Museum, 04580, Install motion detector,
2005 |
| 16 | | | Music 03007, Replace HVAC System Phase 1,
2005 |
| 17 | | | Music 04482 Refurbish Band Room (Room M02),
2005 |
| 18 | | | Music 04868 Fire Safety,
2005 |
| 19 | | | News and Public 04194 Room 102 and 107, Install
Shelves, Cabinet, Pan Under A/C Unit,
2005 |
| 20 | | | North Sewer Lift Station 04077 Replace Valves,
2005 |
| 21 | | | Old Animal Science Building 04535 Add Lighting,
2005 |
| 22 | | | Old English Philosophy 04578 Add Lighting,
2005 |
| 23 | | | Physical Plant 04397 South side Shop's Roofs,
2005 |
| 24 | | | Park and Ride 03965 Security Cameras,
2005 |
| 25 | | | Petroleum Engineering 03393 Walk in Fume Hood Room
206,
2005 |
| 26 | | | Petroleum Engineering 04584 Install Lay-In Ceilings
Room 105A, 106 A,
2005 |
| 27 | | | PrinTech 04145 Renovation,
2005 |
| 28 | | | PrinTech 04477 Add Electrical Circuits and Plumbing,
2005 |
| 29 | | | Psychology 04394 Replace Elevator Valve, Pump, and
Starter,
2005 |
| 30 | | | Rawls Course 04706 Design Storage Shed for equipment,
2005 |
| 31 | | | Reese Center 555 04082 Replace Boiler System,
2005 |
| 32 | | | Reese Center 555 04733 Evaluate Heat Load,
2005 |
| 33 | | | Rugby Field 04089 Install Lighting,
2005 |
| 34 | | | Science 03395 Fume Hood Room 40,
2005 |
| 35 | | | Science 04468 Cooling in server Room 122,
2005 |
| 36 | | | Science 04548 Install an Interwrite Professional
Productivity Solution (PRS) System,
2005 |
| 37 | | | Science 04857 Install Ceiling and Lights in 6 Rooms,
2005 |
| 38 | | | Sneed Hall-Sam's Place 04617 Build wall to hide
grease Barrels at Sam's Place,
2005 |
| 39 | | | Southwest Collection/ Special Collections Library
03002, Repair roof and stone,
2005 |
| 40 | | | Stangel-Murdough Kitchen 04487 Install Chill Water
Lines,
2005 |
| 41 | | | Texas Tech Plaza, 04486, Correct Fire Safety
Deficiencies,
2005 |
| 42 | | | Thompson Hall 04634, Tunnel Repair,
2005 |
| box | folder |
| 94 | 1 | | | TIEHH 552 03821 Provide Standby Generator Electrical
Support for Relocation of Specimen Freezers,
2005 |
| 2 | | | TIEHH 555, 04684 Redesign reheat coils for lab,
2005 |
| 3 | | | TIEHH 555 04812 Evaluate Air handler,
2005 |
| 4 | | | Tunnel Network 03326 Repair Tunnel CHACPI, Ag
sciences, Biology,
2005 |
| 5 | | | Tunnel Network 04165 Install Conduit Path,
2005 |
| 6 | | | United Spirit Arena 03773 Exterior Lighting,
2005 |
| 7 | | | United Spirit Arena 04152, Renovate Double T Shop,
2005 |
| 8 | | | United Spirit Arena 05014 Suite Restroom lights,
2005 |
| 9 | | | UPD-University Police Department 02781 Building
Renovation,
2005 |
| 10 | | | UPD- University Police Departmen 04099 Security
Access,
2005 |
| 11 | | | UPD-University Police Department 04352 Ventilate Room
117, 119, 119 A,
2005 |
| 12 | | | UPD-University Police Department 04460 Relocate
Communications Center to UPD Building,
2005 |
| 13 | | | University Police Department 04690 Add Doors,
2005 |
| 14 | | | Utilities Relocation- Marsha Sharp Freeway 02780,
Utilities Relocation,
2005 |
| 15 | | | Wall-Gates Kitchen 04488, Temporary Wall,
2005 |
| 16 | | | West Hall 03287 Renovate Student Counselling Center-
Rm 214, 1 of 2,
2005 |
| 17 | | | West Hall 03287 Renovate Student Counselling Center-
Rm 214, 2 of 2,
2005 |
| 18 | | | West Hall 03822 Renovate Room 308,
2005 |
| 19 | | | West Hall 03861 Posters, Plants, rugs for student
counselling center,
2005 |
| 20 | | | West Hall 03961 Chairs and "L" Unit mailboxes,
2005 |
| 21 | | | West Hall 03987 Rug for Lobby Area,
2005 |
| 22 | | | West Hall 03992 Terrazo Floor for Visitor Center,
2005 |
| 23 | | | West Hall 04336 Rugs, Shelves, Computer stand rm 214,
2005 |
| 24 | | | West Hall 04377 7 Prints,
2005 |
| 25 | | | West Hall 04386 Table Arrangements- Room 214,
2005 |
| 26 | | | West Hall 04429 5 New Prints and 1 redo,
2005 |
| 27 | | | West Hall 04740 San Antonio Regional Center,
2005 |
| 28 | | | Wiggins Dining 01939, Renovation, 1 of 2,
2005 |
| 29 | | | Wiggins Dinging 01939 Renovation, 2 of 2,
2005 |
| 30 | | | Wiggins Dining 03677 Phase 2 Renovations, 1 of 2,
2005 |
| 31 | | | Wiggins Dining 03677 Phase 2 Renovations, 2 of 2,
2005 |
| 32 | | | Wind Engineering 04803 Wind Turbine and Concrete
Base,
2005 |
Return to the Table of Contents
|